The Department of State Hospitals (DSH) proposes to implement pharmacy modernization that will consist of inventory, unit dose repackaging, automated dispensing, and patient specific medication billing as well as pharmacy data integration requiring rearchitecting the existing pharmacy related application environment to accommodate the new pharmacy system. Pharmacy Modernization will directly improve patient care and hospital operations. In addition, this will allow DSH to effectively track inventory, enhance patient medication safety, capture patient specific medication billing to increase revenues, and decrease the likelihood of drug shortages.
| Agency / State Entity | Health and Human Services / State Hospitals, Department of |
|---|---|
| Total Cost | $24,990,390 |
| Last Approved Start Date | 12/01/2021 |
| Last Approved Finish Date | 02/16/2027 |
| Criticality Rating | Low |
| IPOR Reporting Period | Overall IPOR Rating |
|---|---|
| 05/01/2026 - 05/31/2026 |
Key Questions
Is the project on track to satisfy the customer's business objectives?Yes
Is the project on track to achieve the objectives in the approved timeframe?Yes
Is the project on track to achieve the objectives within the approved budget?Yes
| Project Overall Health | Comments |
|---|---|
| The overall project health rating for this reporting period is Green. Project current status and key accomplishments: • Project Completion Status - 45% complete. • Implementation progress of project milestones across the five hospital sites: - MedSelect: - Completed: DSH-C - In progress: DSH-M and DSH-A - Not started: DSH-N and DSH-P - RxWorks: The RxWorks software did not meet user expectations at DSH-M, resulting in the PSC decision halting its implementation at other hospitals. The CDT was informed of this decision on January 6, 2026. The IPO team is awaiting responses to a set of questions shared with the project team to assess the potential impact of this change on the project scope, cost, and schedule. - Suspended: DSH-C and DSH-M - Not started: DSH-A, DSH-N, and DSH-P - Centrack: - Completed: DSH-C - In progress: DSH-M and DSH-A - Not started: DSH-N, and DSH-P - Verify Spooler: - Completed: DSH-C and DSH-M - In progress: DSH-A - Not started: DSH-N, and DSH-P - The Verify & Spooler component implementation was planned to follow the successful deployment of RxWorks at each hospital site. With the suspension of RxWorks implementation, the Verify Spooler implementation timeline at DSH-A, DSH-P, and DSH-N is being re-evaluated. • Organization Change Management (OCM): - Pharmacy Modernization Project intranet site deployed providing detailed information and a user guide to end users about the project and its various components and systems. - Training plan for RxWorks Support Team developed. - Development of pharmacy-specific training materials in progress. • Fire Marshal permits have been issued for all five hospital sites. • DSH-Coalinga (DSH-C) MedSelect (Deployment completed): - All 33 display terminals of MedSelect at DSH-C are in production. - Hospital-wide MedSelect v 9.1.2 production deployment completed. - MedSelect deployment, training for the MedSelect version 9.1.2, and as-is and to-be workflows are completed. - Planning hospital-wide deployment of MedSelect v 9.1.3 upgrade is in progress. RxWorks deployment suspended. Centrack deployment completed. Verify & Spooler (Deployment completed) - The Verify & Spooler equipment were successfully installed in May 2026 • DSH-Metro (DSH-M) MedSelect (Deployment in progress): - MedSelect deployment planning is in progress. - 29 of 29 MedSelect machines have been installed. - New MedSelect Policy Created. - MedSelect Super User training completed. RxWorks (Deployment completed): - RxWorks was successfully deployed and go-live was on August 26, 2025. - RxWorks training was conducted throughout the month of August. - RxWorks software is live for ordering pharmaceutical products. Verify & Spooler (Deployment completed) - The Verify & Spooler machine was installed, and the necessary end-user training was conducted. - Integration of the existing FastPak machines with RxWorks completed. Centrack (In progress): - Centrack deployment completed. Post-deployment activities in progress. Infrastructure (Completed) - The construction work is completed, and the final inspection has been carried out. • DSH-Atascadero (DSH-A) MedSelect (Deployment in progress): - Planning efforts for the MedSelect Cabinet implementation at DSH-A are in progress. - All of the MedSelect equipment deliveries have been completed. - MedSelect v.9.1.2/Oracle Standard virtual server build completed. - MedSelect v.9.1.3/Oracle Enterprise virtual server build completed. RxWorks (Not started) Centrack (In progress) - Planning for the software version update from v8 to v9 is complete. Verify & Spooler (In progress). Infrastructure (In progress) - Phase 1 of the construction works began in July 2025, and completed in all 35 units. Planning for Phase 2 of construction works are in progress, and the completion target date has moved from June to September 2026. • DSH-Napa (DSH-N) MedSelect (Not started) RxWorks (Not started) Centrack (Not started): - Centrack implementation follows successful MedSelect installation and configuration. Verify & Spooler (Not started). Infrastructure (Planning in progress): - Fire Marshall permits were received in December 2025. - Planning for the construction Invitation For Bid (IFB) is in progress. • DSH-Patton (DSH-P) MedSelect (Upgrade of existing machines is complete) - MedSelect server and software upgrades are complete. - Planning for migration to v9.1.2/Oracle Standard is complete. Migration will follow hospital-wide deployment of v9.1.2 on new machines. RxWorks (Not started) Centrack (Not started): - Centrack implementation follows successful MedSelect installation and configuration. Verify & Spooler (Not started). Infrastructure (Planning in progress): - Fire Marshal permits were received in December 2025. - Planning for construction IFB is in progress. • Project Approval Lifecycle (PAL) - (1/2019 – 4/2022) - PAL Stage 4 was approved in July 2021, and again re-validated in April 2022. |
| Focus Area/Rating | Comments |
|---|---|
| Governance |
The Governance health rating for this reporting period is Green. The project continues to include the pillars of proper project governance: • Structure: The project team, Executive Committee, vendor, and user community are established and follow established roles and responsibilities. • People: The right people with the right skills are in place, and project, vendor, and hospital resources are engaged. • Communication: Consistent information sharing is taking place. Key project information and status are documented and communicated through both push and pull mechanisms. • Decision-Making: Roles and responsibilities are established through an approved Governance plan and project RACI, and decisions are being logged. Note: An Executive Steering Committee is established and meets regularly, and a dedicated meeting for working risks and issues is regularly scheduled, where risk and issue logs are documented and worked on in a consistent manner. |
| Time Management |
The Time Management health rating for this reporting period is Green. Construction at DSH-P and DSH-N has been delayed by six months due to: 1) DGS Form 23 approval taking six months instead of three; 2) new HCAI involvement requirements adding two months; and 3) a three-month delay for the Department of State Architect exemption. The DSH plans to issue the Invitation for Bids (IFB) for each site in July, with construction work expected to begin in October. However, this delay may extend the project timeline by approximately 5%, shifting the completion date from May 2027 to June 2027. As a result of the above-mentioned delays and the recent PSC’s decision not to proceed with the RxWorks implementation, the project team is assessing the impact on the project timeline. Once confirmed, any changes to the project timeline will be reported in future IPORs. |
| Cost & Contract Management |
The Cost & Contract Management health rating for this reporting period is Green. The project experienced a cost variance of over 10%. To address this, the project submitted an SPR to the CDT that was approved on March 5, 2025, re-baselining the project cost. As a result of the recent PSC decision not to proceed with RxWorks implementation, the project team is assessing the impact of removing RxWorks-related activities from the project scope. Any change to the project cost and contract will be reported in the upcoming IPORs. |
| Scope Management |
The Scope Management health rating for this reporting period is Green. The project is on track to achieve the set objectives. The Pharmacy Modernization project will improve patient care and pharmacy operations by implementing an enterprise-wide automated solution across all five state hospitals. The elements of this project are: Inventory (medication) control, medication repackaging and dispensing, secure management of controlled medications, accurate patient billing information, pharmacy data integration across all five hospitals (Coalinga, Metropolitan, Atascadero, Napa, and Patton), and modifications to the existing application environment and architecture to support new hardware and software. |
| Resources |
The Resources health rating for this reporting period is Green. • A full-time state project manager is serving the project and is supported by another project manager on an as-needed basis, along with several DSH team members supporting the overall project effort. • One vendor project manager, along with other technical staff, is supporting the project. |
| Quality |
The Quality health rating for this reporting period is Green. To date, project quality, whether due to vendor products or state activities, has not posed a major problem. However, the high number of MedSelect hardware issues arising on newly installed equipment is being closely monitored. • Quality Assurance planning activities are anticipated to be a collaborative effort with the vendor, pharmacists, and nursing administrators related to quality for the Commercial Off-The-Shelf (COTS) Solution. • Stakeholders are participating in all walkthroughs and evaluations of the most effective equipment configuration for their environment. • Weekly meetings are held with the stakeholders to review what is working well and what areas need improvement during the implementation phases of the project. • Lessons Learned sessions are scheduled with the objective of applying Lessons Learned to the remaining hospital sites’ implementations. |
| Risk And Issues |
The Risks and Issues health rating for this reporting period is Green. In response to the IPO team's recommendation to improve risk and issue identification, the project team has implemented several actions outlined on Page 27 of this report. The IPO team verified these actions through ongoing oversight of the risk and issue management process. Consequently, the health rating for this focus area has changed from yellow to green in this reporting period. Due to the PSC’s recent decision to remove RxWorks from the project scope, with no prior relevant risk identified or communicated, the health rating for this focus area changed from green to yellow in the previous reporting periods. Based on the project team’s responses to a series of questions from the IPO team, it appears that, despite user dissatisfaction with the initial rollout of RxWorks at the DSH-M hospital site, the project team did not identify or document any potential risks related to this issue that eventually led to project descoping. Consequently, the health rating for this focus area remained yellow in the previous reporting period, while the IPO continued to monitor the risk management process before considering a reversion to green. Aside from the above instance, the IPO team confirms that the project team conducts regular meetings and maintains thorough records as follows: • Weekly project meetings are scheduled and regularly held, allowing stakeholders and end users to raise risks and issues. • Weekly scheduled meetings dedicated to addressing current risks and issues are regularly held with the stakeholders and the vendor. • A comprehensive issue log is maintained, and action plans are expediently developed to address open issues. • A comprehensive risk log is maintained and includes risk response strategy, planning, and contingency planning. |
| Transition Readiness |
The Transition Readiness health rating for this reporting period is Green. As part of Transition Readiness, the team is currently working with the vendor on future workflows and demonstrations to ensure all organizational change management elements are documented, reviewed, and approved. Additionally, stakeholders are involved throughout the project, participating in all walkthroughs and evaluations of the equipment configurations to ensure they are effective for their specific environments. |
| Conditions For Approval |
There are no Conditions for Approval. |
| Corrective Action |
There are no Corrective Action Plan Items. |