Independent Project Oversight Report (IPOR) Rating

8950-059 CalVet Electronic Health Record (CEHR)

The California Department of Veterans Affairs proposes to replace the existing Veteran Home’s electronic health records system.

Project Details

Agency / State Entity General Government / Veterans Affairs, Department of
Total Cost $39,067,807
Last Approved Start Date 03/09/2020
Last Approved Finish Date 10/16/2026
Criticality Rating Medium
IPOR Reporting Period Overall IPOR Rating
04/01/2026 - 04/30/2026
Green
Independent Project Oversight Dashboard

Key Questions

Is the project on track to satisfy the customer's business objectives?Yes

Is the project on track to achieve the objectives in the approved timeframe?Yes

Is the project on track to achieve the objectives within the approved budget?Yes

Project Overall Health Comments
Green
The CEHR Project is rated Satisfactory (GREEN) as overall the project is progressing in alignment with the project’s schedule and costs to the approved SPR 3 timeline and budget baseline.
Focus Area/Rating Comments
Governance

yellow icon Yellow
This focus area is rated Cautionary (Yellow). • Executive Status Meetings (ESC) continue on a monthly basis but remain inconsistent with the Governance Plan v4.0 Roles and Responsibilities.
Time Management

green icon Green
This focus area is rated as Satisfactory (Green). • Project end date is “on schedule” per the CDT approved SPR3 baseline. • Project Status and Schedule reporting is submitted timely.
Cost & Contract Management

green icon Green
This focus area is rated Satisfactory (Green). • Project expenditures to date align with the Financial Analysis Worksheets (FAW) of the approved SPR 3 baseline. • Unanticipated Task funding is expended, and additional Change Requests (CRs) are not critical to project completion.
Scope Management

green icon Green
This focus area is rated Satisfactory (Green) but trending Cautionary (Yellow) due to potential risks in meeting project goals and objectives. • Project is nearing the end of its Execution Phase and some updates or validations for To-Be Business Process Models (BPM)s remain pending (C.2, C.4 and C.6).
Resources

green icon Green
This focus area is rated Satisfactory (Green) trending Yellow. • Existing resources have managed to alleviate significant gaps in coverage needed for Go-Live readiness and UAT best practices. • CalVet Health Informatics Program (CHIP) resource constraints appear to be a bottleneck for CEHR team and SME leads to complete essential tasks.
Quality

green icon Green
This focus area is rated Satisfactory (Green) but trending Yellow. • UAT and EOE tasks are increasing, which further constrains resources in areas of Policy and Compliance, OCM and Testing/Requirements management. • M&O Plan draft V5.0 still remains under review with no target completion date set.
Risk And Issues

yellow icon Yellow
This focus area remains Cautionary (Yellow) but trending Green. • Concerns with identified risks not being analyzed consistently or early enough to assess impact on project objectives have improved. • Contingency planning is being discussed but not well documented to date.
Transition Readiness

green icon Green
This focus area is rated Satisfactory (Green) as there is a significant amount of collaboration between OCM Lead and Home SMEs/Administrators and project team SMEs/PM and PD • OCM Plan update is still pending final approval.
Conditions For Approval

green icon Green
No conditions for approval.
Corrective Action

green icon Green
No corrective action plans are required at this time.
Project Approval Documents
Website Accessibility Certification

20250626 Release-16