7100-237 Document Management System (DMS)
The EDD has analyzed a variety of existing software solutions used for its existing imaging, data capture, electronic file submissions, document storage, and retrieval services infrastructure. The proposed vendor solutions must provide the capability to develop processes that are streamlined, scalable, and flexible for variable workloads. The solution features should support the deployment of new configurable, scalable, and robust software for imaging paper and electronic submissions as well as efficiently process defined business workflows. The DMS project will provide foundational capabilities necessary to support EDD modernization and GovOps Strike team recommendations.
Project Details
| Agency / State Entity | Labor and Workforce Development / Employment Development Department |
|---|---|
| Total Cost | $141,016,059 |
| Last Approved Start Date | 06/17/2024 |
| Last Approved Finish Date | 10/25/2027 |
| Criticality Rating | Medium |
| IPOR Reporting Period | Overall IPOR Rating |
|---|---|
| 10/01/2026 - 10/31/2026 |
Independent Project Oversight Dashboard
Key Questions
Is the project on track to satisfy the customer's business objectives?Yes
Is the project on track to achieve the objectives in the approved timeframe?No
Is the project on track to achieve the objectives within the approved budget?No
| Project Overall Health | Comments |
|---|---|
| The overall project status is Yellow for the following reasons: o The EDD Executives are reviewing the Non-Competitive Bid and Contract Amendment. The project team will provide additional information by the end of November 2026. |
| Focus Area/Rating | Comments |
|---|---|
| Governance |
o The IPO Manager has recommended that the DMS project team include the Labor and Workforce Development Agency in the Change Control Board (CCB), Executive Working Group (EWG) and Governance Escalation Group (GEG) meetings. The project team is reviewing the recommendation and the Governance Management Plan. |
| Time Management |
o The timing of the overall project completion including the Release 3 and Release 4 functional and data migration go-live dates is uncertain. |
| Cost & Contract Management |
o The CDT approved the Special Project Report (SPR)#1 on October 15, 2026. The project team updated the October 2026 Project Status Report (PSR) based on the FAW’s dated August 27, 2026. o The potential cost impacts associated with the additional scope proposed under CR#4 and CR#6 is currently under review to assess the justification and reasonableness of the proposed costs. |
| Scope Management |
o The additional scope included in Change Requests (CR) #4 and #6, which the project team has identified as necessary to complete the transition from the legacy system, is currently under review, which would help determine the justification for the proposed scope changes. |
| Resources |
o The System Integrator (SI) decided to halt work on the DMS project. However, certain project management activities continued. |
| Quality |
o The project team informed the stakeholders that they decided to go-live with seventeen (17) outstanding low or medium level defects found during Regression Testing. The IPO Manager recommended that the project team fix the remaining defects found during Regression testing since the new go-live had not been finalized. o The project team accepted the IPO Manager’s recommendation and fixed seven (7) defects found during Regression testing. |
| Risk And Issues |
o The project team appears to be following the processes outlined in the Risk and Issue Management plan. |
| Transition Readiness |
o The System Integrator has created a technical knowledge transfer plan. The technical team shared a detailed list of 35 plus knowledge transfer sessions which are being scheduled over the next few months. |
| Conditions For Approval |
All conditions for PAL Stage Gate approvals have been met. |
| Corrective Action |
Comments about Corrective Action Plan Items • N/A |