Independent Project Oversight Report (IPOR) Rating
-
- Satisfactory, no corrective action necessary.
-
- Caution, risks/issues exist. There may be a need for corrective action in the near future.
-
- Escalated for immediate corrective action. There is a significant risk to the health of the project.
-
- Not enough data is available to make a determination about the project health.
-
No Report Available - Indicates that a Report is not available for publishing for the reporting period.
3480-052 Division of Mine Reclamation DMR SMARA-4
A new data management system that will allow operators and lead agencies secure access to submit required information, documents, and fees to the Division of Mine Reclamation (Division), California Geologic Survey (CGS), and California State Mining and Geology Board (SMGB) as required under the Surface Mining and Reclamation Act (SMARA) via a web interface. Information collected would be stored in a data management system that allows the Division, CGS, and SMGB to effectively implement statutory responsibilities and to provide a level of oversight required under the statutes for SMARA, public contracting (PCC 10295.5 &20676), real estate disclosure (CA CIV § 1103.4), and transparency purposes. Data and information would be made available to the public through a Geographic Information System (GIS) Interface.
Project Details
| Agency / State Entity | Natural Resources / Conservation, Department of |
|---|---|
| Total Cost | $8,107,057 |
| Last Approved Start Date | 06/29/2026 |
| Last Approved Finish Date | 06/29/2027 |
| Criticality Rating | Medium |
| IPOR Reporting Period | Overall IPOR Rating |
|---|---|
| 10/01/2026 - 10/31/2026 |
Independent Project Oversight Dashboard
Key Questions
Is the project on track to satisfy the customer's business objectives?Yes
Is the project on track to achieve the objectives in the approved timeframe?Uncertain
Is the project on track to achieve the objectives within the approved budget?Uncertain
| Project Overall Health | Comments |
|---|---|
| The overall status of the Project is in green. Discovery has been completed and the Project is in its first Release of four planned and Sprint 1 of 12. A new schedule and design documentation is in review. Oversight has provided recommendations to continue to strengthen project practices in alignment to project plans and best practices. |
| Focus Area/Rating | Comments |
|---|---|
| Governance |
• The Project appears to be following their documented Governance practices within its Project Management Plan. • This month the Project has started having weekly status update meetings with the primary vendor and IV&V. |
| Time Management |
• The vendor has provided a new draft schedule for review that aligns to the Project’s Agile approach, four Releases with three Sprints each. • If there is a schedule variance of more than ten percent (10%), an SPR may be required. • The Project appears to be following their documented Schedule Management practices within its Project Management Plan. |
| Cost & Contract Management |
• The Project appears to be following their documented Cost and Contract Management practices within its Project Management Plan. |
| Scope Management |
• The Project appears to be following their documented Scope Management practices within its Project Management Plan. • The vendor provided a draft Design Document that is under review. • Oversights recommends the vendor provide a Requirement Traceability Matrix. |
| Resources |
• The Project appears to be following their drafted Resource Management practices within its Project Management Plan. • An open recommendation remains that resources are clearly identified in the schedule so that Project can plan accordingly. |
| Quality |
• The Project appears to be following their documented Quality practices within its Project Management Plan. • IVV has been reviewing the Project plans and artifacts and is providing adequate feedback on possible improvements and identifying gaps. • Oversight recommends developing a Deliverable Tracker that clearly identifies reviewers and approvers for each deliverable. |
| Risk And Issues |
• The Project appears to be following their documented Risks and Issues practices within its Project Management Plan. |
| Transition Readiness |
• The Project has established Maintenance and Operations Transition practices within its Project Management Plan. • There have been no observable changes to Transition Readiness for this reporting period. |
| Conditions For Approval |
• There are no conditions for approval in place. |
| Corrective Action |
• There are no corrective action plans in place. |
Green
Yellow
Red
Blue