Independent Project Oversight Report (IPOR) Rating
-
- Satisfactory, no corrective action necessary.
-
- Caution, risks/issues exist. There may be a need for corrective action in the near future.
-
- Escalated for immediate corrective action. There is a significant risk to the health of the project.
-
- Not enough data is available to make a determination about the project health.
-
No Report Available - Indicates that a Report is not available for publishing for the reporting period.
0840-086 California State Payroll System Project (CSPS)
The State Controller's Office (SCO) and The California Department of Human Resources (CalHR) have partnered to move from the legacy State Payroll System to a new suite that will modernize payroll and core HR services. SCO and CalHR, leveraging lessons learned from the terminated 21st Century project, have undertaken a comprehensive planning effort that includes normalization of payroll practices for the State that will allow it to utilize proven solutions instead of custom development to better position them for success.
Project Details
| Agency / State Entity | Legislative, Judicial, and Executive / State Controller |
|---|---|
| Total Cost | $1,240,698,857 |
| Last Approved Start Date | 04/10/2025 |
| Last Approved Finish Date | 09/24/2031 |
| Criticality Rating | High |
| IPOR Reporting Period | Overall IPOR Rating |
|---|---|
| 10/01/2026 - 10/31/2026 |
Independent Project Oversight Dashboard
Key Questions
Is the project on track to satisfy the customer's business objectives?Yes
Is the project on track to achieve the objectives in the approved timeframe?Yes
Is the project on track to achieve the objectives within the approved budget?Yes
| Project Overall Health | Comments |
|---|---|
| The overall project health rating is green for the October 2026 reporting period. • The Executive team participated in the California Center for Government Innovation (CCGI) Emerging Technologies Forum on October 15, 2026. • CSPS team debuted a new kiosk at the 2026 CalHR Annual Conference providing hands-on access to the new solution. |
| Focus Area/Rating | Comments |
|---|---|
| Governance |
• The Independent Project Oversight Managers (IPO) observed that project leadership, executives, and workstream teams remain engaged and are actively assisting with solution decisions blocking the development of functional scope. • The project follows a regular cadence for Executive Steering Committee (ESC) meetings. The most recent ESC meeting was held on October 22, 2026. No decisions were requested or escalations discussed during the meeting. • Change Request (CR)# 011- Help Desk Resource Needs, which is related to the implementation of Customer Contact Center (CCC), was approved by ESC members and is currently routing for final signatures. • Approval of CR#11 will have the following impacts: - Cost: An increase of $3.34M for FY 2026-27, with an overall increase of $11.55M through 2032-33. Current year and total variance from approved project costs is pending. - Resources- Addition of six (6.0) resources to support CCC implementation and ongoing operations. These resources were already accounted for as production resources in the approved baselines. - Schedule- no impact identified yet; final impact will be determined upon contract execution and execution timeline. |
| Time Management |
• This focus area is trending yellow due to a six-week reassessment period for the CSPS and Fi$Cal integrations. Schedule impact will be determined at the conclusion of this effort, estimated December 11, 2026. • The Agile Development is 70% complete and Planning Interval (PI) 4 development is 33% complete. • To address and accelerate the resolution of open Analysis Tasks (ATs) and Information Requests (IRs) blocking PI 4 development, the PMO team is collaborating with the functional team. The tasks have been grouped by specific subject areas, and a dedicated surge task force has been assigned for the analysis. The IPO will continue to monitor the resolution of these tasks and impact to development. • The IPO observed that the project continues to actively track the progress of key tasks, deliverables, and sprint activities against the project schedule. The IPO will continue to monitor task completion relative to the schedule as the project progresses. |
| Cost & Contract Management |
• The costs reported reflect the actual costs through September 2026. • Costs reported for this assessment period: -- Total actual one-time costs (project + planning): $239M, which represents 62% of the allocated budget of $386M through 2026-27. -- Total project costs: $152M, which represents: > 16% of the approved project costs of $938M > 52% of the approved project costs of $294M through 2026-27. • The annual Joint Legislative Budget Committee (JLBC) report for the CSPS project was sent to the Legislature on October 1, 2026. • The project received $14.3M in Department Agency Readiness Team (DART) funding for FY 2025-26 and approved reimbursement requests of $1.45M from departments. The remaining balance of $12.79M for FY 2025-26 was reverted to the Department of Finance (DOF). • The project has eight (8) active contracts. The contract costs are within budget. |
| Scope Management |
• This focus area is yellow due to the pending addition of CCC to scope and potential reduced scope for Fi$Cal interfaces. • Requirement Changes from ATs analysis continue to trigger additional Change Requests (CR). The Solution Integrator (SI) is conducting impact analysis for CR#12 and #13. • CalHR/Policy Updates: -- Continues to analyze user stories to determine the need for policy revisions or new policy development. -- Continues 2026 union outreach efforts with the SEIU meeting held on October 8, 2026, and CSPS Union Townhall meeting held on October 20, 2026. |
| Resources |
• The overall resource variance reduced to 9%. The project reported that fourteen (14.0) of the one hundred twelve (112.0) SCO-authorized positions and two (2.0) of the twenty-five (25.0) CalHR-authorized positions remain vacant. • The IPO observed that the team continues to actively recruit open positions and replacements for contractor staff. The IPO will continue to track resource needs and ensure appropriate resources are maintained as the project progresses. |
| Quality |
• The team continues development activities for PI 4. Sprint 2 completed on 10/26/2026 with an average commit-to-complete ratio of 100%. • The development team continues to make good progress on PI 4 and remains confident in completing the planned 2,500+ story points by December 2026. However, ongoing resolution of pending ATs and IRs continues to add work each week, creating increased pressure on planned scope and schedule. As a result, the team cannot yet reliably assess the resulting scope and schedule impacts ahead of the PI 4 December 2026 target. Upcoming holidays and planned vacations may further impact delivery. The IPO recommends that leadership proactively evaluate mitigation strategies and delivery options rather than defer decisions until December 2026. • The SI submitted the monthly status report for this assessment period on November 9, 2026. The report lists two new risks related to completion of PI 4 and unit testing of conversion data. Mitigation strategies for these risks are being evaluated. • The IV&V team submitted the draft Monthly Activity Report (MAR) on November 5, 2026. The team identified two (2.0) Medium risks and two (2.0) Medium-High risks. Discussions with the project team are in progress, and the new risks have not yet been finalized. The observations shared in the MAR are consistent with the IPO's overall assessment of the project's health. |
| Risk And Issues |
• The project is actively managing, monitoring, and tracking the risks and issues. • The project continues to track the following high Priority issue: Issue#36- Current Travel and Expense Future State Design Does Not Accommodate Functional Needs. This issue will be revisited as the CSPS-Fi$Cal task force discussions progress. • The project is tracking the following top risks* in each category. Near-Term risks (less than three (3) months): - Risk# 5–Project Resource Availability. - Risk# 18910 – Unavailable Schedule Reserve. - Risk# 18844- Implementation of Centralized Contact Center (CCC). Long-term risks (greater than three (3) months): - Risk# 18856- Lack of HCM System Standardization Resulting in Duplication, Delays, and Reduced Satisfaction. - Risk# 18828 – Lack of Production Support Resources for Production Operations. - Risk# 18847 – Lack of Subject Matter Experts Availability during DDCI. * For further information on the above risks, refer to the Risks & Issues focus area details section. |
| Transition Readiness |
• The Organizational Change Management (OCM) team continued to advance readiness, communications, training, and stakeholder engagement activities during this assessment period: - preparing demos for the Department Agency Readiness Team (DART) meeting to be held in November 2026 - developing System and Navigation training materials for User Acceptance Test (UAT) - analyzing survey results from the Modernizing Pay Day (MPD) campaign. |
| Conditions For Approval |
The project has the following conditions of approval as per the superseded Stage 4 Approval Letter issued on May 15, 2025. The project is working on meeting these conditions by the specified due date. 1) Within 90 days of this letter, the SCO shall submit to the CDT a detailed, fully resource-loaded CSPS Integrated Master Schedule (IMS), which includes both State and System Integrator (SI) activities, deliverables, milestones, and tasks -- The project submitted the approved IMS/MPS to CDT on August 12, 2025. 2) Within 90 days of this letter, the CSPS Project Management Team shall review, and the SCO shall approve and submit updated Project Management Plans to the CDT. -- The project submitted approved plans to the CDT on September 2, 2025, and has met this condition of approval. 3) Following the start of project implementation, the SCO shall submit to the CDT the Independent Verification & Validation (IV&V) Monthly Status Report. -- The project is meeting this condition of approval with the monthly submission of the IV&V report. 4) No later than 60 days prior to the initiation of testing activities by the SI, the SCO shall submit the approved CSPS Project Test Management Plan to the CDT. -- The project submitted the approved plan to CDT on December 1, 2025, and has met this condition of approval. 5) In accordance with the State Administrative Manual (SAM) Section 4946 and the State Information Management Manual Section 160, the project shall submit a Transition to Maintenance and Operations Plan, including the plan for any transition of services from the SI vendor to the State, to the CDT for review and approval six months before the approved project end date. |
| Corrective Action |
N/A |