Independent Project Oversight Report (IPOR) Rating
-
- Satisfactory, no corrective action necessary.
-
- Caution, risks/issues exist. There may be a need for corrective action in the near future.
-
- Escalated for immediate corrective action. There is a significant risk to the health of the project.
-
- Not enough data is available to make a determination about the project health.
-
No Report Available - Indicates that a Report is not available for publishing for the reporting period.
4440-126 Continuum Electronic Health Record (EHR)
The Department of State Hospitals proposes to implement the core functionality of an electronic health record in order to address crucial business needs related to standardized patient registration, pharmacy inventory management, and billing operations.
Project Details
| Agency / State Entity | Health and Human Services / State Hospitals, Department of |
|---|---|
| Total Cost | $460,356,108 |
| Last Approved Start Date | 06/01/2026 |
| Last Approved Finish Date | 11/30/2028 |
| Criticality Rating | High |
| IPOR Reporting Period | Overall IPOR Rating |
|---|---|
| 10/01/2026 - 10/31/2026 |
Independent Project Oversight Dashboard
Key Questions
Is the project on track to satisfy the customer's business objectives?Yes
Is the project on track to achieve the objectives in the approved timeframe?Yes
Is the project on track to achieve the objectives within the approved budget?Yes
| Project Overall Health | Comments |
|---|---|
| • The detailed schedule (System Implementation Schedule, deliverable 3.4) was not submitted as planned in October. It is now expected in November and of increasing concern. • The CDT IPO team notes that three Development Deliverable Expectation Documents (DEDs) are overdue and five Deliverables (DELs) were not submitted by September 29, 2026 (120 days from contract start). • The CDT IPO team attended the October Solution Review sessions and observed healthy discussion, engagement, and at times attendees challenging the presenters. • The CDT IPO team continues to monitor progress in filling open Project positions. • The CDT IPO team continues to attend the weekly EHR Risk and Issue meetings. |
| Focus Area/Rating | Comments |
|---|---|
| Governance |
• The IPO team and the EHR project director met for the initial IPO-EHR project director meeting on October 5, 2026. • At the October 28, 2026, EHR Steering Committee (SteerCo) meeting, members discussed the October solution review, escalations, risks, and resource management. |
| Time Management |
• A more detailed schedule (System Implementation Schedule, deliverable 3.4) was due in September to further refine the schedule, document more granular information on the remainder of implementation, testing, data migration and conversion, system cutovers, and go-lives • Deliverable 3.4 was not submitted as planned in September, nor in October, and is now anticipated in November. • The IPO team will continue to monitor the progress of the System Implementation Schedule deliverable and will review the critical path once it is submitted. |
| Cost & Contract Management |
• The Project has an approved budget to achieve the business vision and objectives. • The Project has Cost Management and Contract Management plans. • IPO assessments for this focus area may include review and analysis of cost management and contract management plans, processes, methods, tools, and information. |
| Scope Management |
• The CDT IPO team continues to monitor the 18 vendor DEDs and associated DELs. • The CDT IPO team notes three DEDs are overdue and five DELs were not submitted by September 29, 2026 (120 days from contract start) and were still overdue in October. • DSH is working to revise certain due dates in conjunction with refining the detailed project schedule. • The CDT IPO team attended the October Solution Review sessions and observed healthy discussion, engagement, and at times attendees challenging the presenters. |
| Resources |
• The IPO team continues to monitor progress in filling open Project positions. • Three vendor positions were added and filled in October. • The vacancy rate is 39%. • The DSH is planning to conduct a block interview session for multiple open positions, with CalHR representation and same day offers to expedite hiring |
| Quality |
• Analysis of this focus area will be included in future reporting periods as information becomes available. • The Project has a Quality Management plan. • IPO assessments for this focus area may include review and analysis of EHR quality management plan, processes, methods, tools, and information. • IPO assessments for this focus area may reference findings, risks, and issues communicated by the EHR Independent Verification and Validation (IV&V) vendor and Project stakeholders. |
| Risk And Issues |
• The IPO team continues to attend the weekly EHR Risk and Issue meetings. • The Project Risk Manager effectively uses the weekly meeting to review both risks and issues in the scheduled time, prompting updates/progress from the risk or issue owner. |
| Transition Readiness |
• The Project has a Maintenance and Operations Transition Management plan. • The Project has engaged a vendor for OCM support since May 2024. • The IPO team continues to attend the weekly EHR OCM Project Director Check-In meetings. |
| Conditions For Approval |
The single Stage 4 condition (onboard IV&V) was completed in June 2026. |
| Corrective Action |
None |