Independent Project Oversight Report (IPOR) Rating

Back to Listing

2740-227 Digital Experience Platform (DXP)

The Department of Motor Vehicles (DMV) proposes modernization of the Department’s legacy applications and systems. The modernization of DMV technology is critical to reduce reliance on obsolete, unsupported, and failing technology. This will transform and streamline DMV services delivery to Californians as well as providing DMV the ability to address current and evolving business objectives.

Project Details

Agency / State Entity Transportation / Motor Vehicles, Department of
Total Cost $767,138,511
Last Approved Start Date 09/09/2021
Last Approved Finish Date 03/30/2029
Criticality Rating High
IPOR Reporting Period Overall IPOR Rating
10/01/2026 - 10/31/2026
Yellow
Independent Project Oversight Dashboard

Key Questions

Is the project on track to satisfy the customer's business objectives?Uncertain

Is the project on track to achieve the objectives in the approved timeframe?No

Is the project on track to achieve the objectives within the approved budget?Uncertain

Project Overall Health Comments
Yellow
During the October 2026 assessment period, the project’s overall health is yellow, trending red. Phase 1 OL: Control Cashiering/Inventory Management (CC/IM) functionality go-live date is being replanned. Phase 2 VR: Due to continued testing delays, the Executive Steering Committee extended the go-live date of January 19, 2027, to November 15, 2027. The new date is documented in the Special Project Report (SPR) #3, per Independent Project Oversight (IPO) recommendation. The CDT is observing the effectiveness of a new Product-Oriented Delivery (POD) team to accelerate development and testing. Phase 3 DL/ID: The DMV completed onboarding four of five workstreams. Vendors responded to the pre-solicitation in mid-October. Special Project Report #3 was formally submitted to CDT on October 5, 2026.
Focus Area/Rating Comments
Governance

Yellow
During the October 2026 assessment period, the project’s Governance Management health is yellow, based on observations and analysis of governance processes. • DMV leadership continues to improve VR defect and release management processes, focusing on velocity and quality. • SPR #3 was approved by the California State Transportation Agency (CalSTA) to add Assembly Bill (AB) 1766 scope, extend the project timeline, and increase the total project cost. • DL/ID Governance project meetings were established and running in October, and CDT is attending.
Time Management

Red
During the October 2026 assessment period, the project’s Time/Schedule Management health remains red based on observations and analysis of the Project Schedule Milestones and Deliverables. • VR System Integration Testing (SIT) velocity remains slower than planned. The revised SIT end date was missed, and the projection is now June 4, 2027. • VR Development defect remediation velocity in October was too slow to maintain the schedule. • The VR Development team successfully deployed Package 19. • Condition #5 of SPR #2, which required the team to decompose the Phase 3 - DL/ID roadmap into a Master Project Schedule by November 1, 2026, was met on October 30, 2026.
Cost & Contract Management

Green
During the October 2026 assessment period, the project’s Cost & Contract Management health improved to green, based on observations and analysis of the project’s costs and contracts • Cost is tracking within the approved budget. • The contract management processes have improved and are effective. • The pre-solicitation for the DL/ID Request for Proposal (RFP) was released in September, and responses were received October 15, 2026. • In October 2026, the DMV awarded three contracts for the VR phase (Data Warehouse, Control Cashiering, and Staff Aug). • In October 2026, the DMV awarded four new DL/ID contracts (Human Capital Design, Foundational Services, Data Profiling, and Legacy Services Sync). • Two contracts were awarded for the overall project in October 2026, (Advisory Support and Salesforce and Mulesoft Services). • CDT recommends the PMO produce a deliverable-level responsibility matrix across all DL/ID workstreams and separate contractors. • CDT recommends that the DL/ID contractors and DMV contract managers document deliverables and deliverable expectations to help delineate each team's responsibilities.
Scope Management

Red
During the October 2026 assessment period, the project’s Scope Management health remained red, based on observations and analysis of the project’s scope and related processes. • The CDT recommends the project prioritize urgent defects before Change Requests (CRs). • The change management process is effective. • The Requirements Traceability Matrix (RTM) reports remain incomplete, but the team is making progress on the exception reports. • The Executive Governance Committee has approved eleven CRs for implementation with go-live, canceled two, deferred five, and rejected two. One is new.
Resources

Yellow
During the October 2026 assessment period, this focus area remained yellow. • The overall vacancy rate remains high at 30%, with 33 vacant positions of 109 authorized. • Leadership approved additional consulting resources for VR and is evaluating redirecting Salesforce developers to assist. • The project is accelerating the recruitment process for vacant positions to minimize risk of overlapping DL/ID work with Phase 2 - VR.
Quality

Red
During the October 2026 assessment period, the project’s Quality Management health is red based on observations and analysis of Quality metrics and performance. • The VR SIT initial pass rate improved in October: From 17% for Key Functions to 24%, From: 35% for Pre-Integration to 37%, and from 29% for Comprehensive test cases to 30%. • VR Rank 0 improved from 11% pass to 20% pass with 77% executed. • The CDT recommends the project strengthen DL/ID requirements traceability and validation processes early to avoid downstream rework.
Risk And Issues

Green
During the October 2026 assessment period, the project’s Risk and Issue health remains green. • The risk and issue management process is effective and remains green for October. • The leadership team is actively working on the continued low testing velocity issue. • The project will follow the established Risks and Issue Project Management Plan and processes for the DL/ID phase. • The CDT’s independent observations of the highest risks impacting the project are: o VR Testing velocity o Scope creep o Overlapping VR SIT with User Acceptance Testing (UAT) o VR Code quality issues o External dependencies, such as business partners o Technical cutover data challenges o Phase 3 DL/ID requirements, schedule, resources, and cost, including adding AB 1766 scope.
Transition Readiness

Red
During the October 2026 assessment period, the project’s Transition Readiness health was red based on observations and analysis of the activities performed and plans for VR cutover. • Training delivery timeline and quality were high risk during October due to software defects and will be revised in November based on the new schedule. Trending yellow. • The new VR partner testing dates need to be revised and communicated. • The CDT recommends the DL/ID phase training team engage with the VR training team to develop a schedule and plan logistics, leveraging lessons learned from Phase 2- VR.
Conditions For Approval

Green
There are five conditions associated with SPR #2 approval. • All conditions have been met.
Corrective Action

Green
The project has no Corrective Action Plan Items.
Project Approval Documents