7350-095 Labor Enforcement Task Force Public Works Modernization (LETF PW) Project

Pursuant to Assembly Bill 175 (Chapter 255, 2021), the sum of $30,000,000 was appropriated from the Labor and Workforce Development Fund for support of The Department of Industrial Relations (DIR) for strategic enforcement focused on construction, alteration, and repair projects, subject to the provisions of Section 1785 of the Labor Code. $10,000,000would be allocated to DIR OIS in an effort to upgrade the current Public Works data systems and create a technical capability for analytics using this data.

Project Details

Agency / State Entity Labor and Workforce Development / Industrial Relations, Department of
Total Cost $64,619,163
Last Approved Start Date 06/22/2023
Last Approved Finish Date 10/31/2026
Criticality Rating Medium
IPOR Reporting Period Overall IPOR Rating
08/01/2026 - 08/31/2026
Green
Independent Project Oversight Dashboard

Key Questions

Is the project on track to satisfy the customer's business objectives?Yes

Is the project on track to achieve the objectives in the approved timeframe?Yes

Is the project on track to achieve the objectives within the approved budget?Yes

Project Overall Health Comments
Green
Overall project health remains Green (Satisfactory)- The project remains stable throughout Phase 1 Maintenance and Operations, with no impact to core services. IPO Manager observed from weekly update meetings, the project is on track making progress laying a strong foundation for the September technical validation phase.
Focus Area/Rating Comments
Governance

Green
The Governance Management focus area is in satisfactory status because: No new escalations or unresolved decisions raised during the August 2026 observation period. Governance meetings were held consistently during the reporting period. Revised procurement timeline, DIR analyzing SPR 2 DOF comments and updating.
Time Management

Green
Time Management remains Green (Satisfactory)- IPO Manager observed during the reporting period of August 2026. Currently on track per schedule.
Cost & Contract Management

Green
Cost and Contract Management focus area is in satisfactory status because: Expenditures remain within approved baseline. Continued reliance on interim M&O support and timing of SI support remain key cost management considerations. IPO Manager will continue to observe contract management coverage.
Scope Management

Green
Scope Management remains Green (Satisfactory)- No scope changes, additions, or deferrals were identified. There is a risk that the Release 2 scope may exceed the SI’s planned budget and schedule for which SPR 2 has been submitted and is awaiting project team updates.
Resources

Green
Resources remain Green (Satisfactory)- Resources remain adequate for Phase 1 M&O and Phase 2 procurement activities. IPO Manager observed no resource deficiencies during the reporting period.
Quality

Green
Quality Management remains Green (Satisfactory)- M&O quality controls continue to function. Changes undergo end-user acceptance testing prior to production deployment. No quality issues reporting in the August 2026 reporting period.
Risk And Issues

Green
Risks and Issues remain Green (Satisfactory)- IPO Manager observed weekly meeting discussions to track capacity for potential remediation tasks resulting from security compliance reviews. Risks and issues are being proactively monitored and addressed. Security review related remediation capacity is being tracked, and engagement of a security SME reflects active mitigation. No risks escalated during the reporting period, and no impact was observed to schedule, scope, or cost baselines for the reporting period.
Transition Readiness

Green
Transition Readiness is Green (Satisfactory)- IPO Manager observed in August reporting period meetings that several functional and technical transition tasks still require completion. Environment patching activity completed as scheduled, but defect leakage identified post‑refresh requires short‑term remediation work. No impact on the critical path has been detected; project leadership monitors environmental stability closely.
Conditions For Approval

Green
Complete.
Corrective Action

Green
None.