The California Department of Fish and Wildlife (CDFW) proposes to update the statewide online permitting systems, Environmental Permit Information Management System (EPIMS) and Scientific Collecting Permit Portal (SCPP). The scope will also include improving operational efficiency in management of environmental permits by supporting other critical Environmental Review processes including online application and tracking of California Endangered Species Act (CESA) Take Permits whose tracking platform known as Project Tracking is no longer supported. The goal of this project is to create one system that can incorporate these systems.
| Agency / State Entity | Natural Resources / Fish and Wildlife, Department of |
|---|---|
| Total Cost | $13,317,754 |
| Last Approved Start Date | 01/07/2025 |
| Last Approved Finish Date | 01/06/2027 |
| Criticality Rating | Medium |
| IPOR Reporting Period | Overall IPOR Rating |
|---|---|
| 04/01/2026 - 04/30/2026 |
Key Questions
Is the project on track to satisfy the customer's business objectives?Uncertain
Is the project on track to achieve the objectives in the approved timeframe?No
Is the project on track to achieve the objectives within the approved budget?Uncertain
| Project Overall Health | Comments |
|---|---|
| • In April, project remains paused until the vendor can deliver acceptable documentation related to Permit #1 Incidental Take Permits (ITP) and a realistic path forward. • DFW and the Independent Validation and Verification (IV&V) contractor has provided the vendor with feedback and suggested strategies to help with forward progress. • The Project conducted in-person JAD sessions for three full days in mid-April in order and made some progress. • Once a realistic revised schedule is identified, the DFW will work to gain DFW executive approval, per the Project’s governance process and complete a Special Project Report (SPR) to submit to the CDT. |
| Focus Area/Rating | Comments |
|---|---|
| Governance |
• A Governance Structure has been agreed to and documented in the project planning process. |
| Time Management |
• The Project has an acceptable Schedule Management Plan. • IPO has observed the Project falling behind in completing deliverables related to Permit #1, with discovery activities for Permit #2 and #3 on hold until Permit #1 ITP is complete. • An updated project schedule is being prepared by the vendor. • The Project is now in the sixteenth month of execution and has not updated the schedule based on discovery session findings. |
| Cost & Contract Management |
• The Project has an acceptable Cost Management Plan and Contract Management Plan. • IPO has witnessed the Project executing and adhering to the Cost and Contract Management Plans. |
| Scope Management |
• The Project has an acceptable Scope Management Plan. • IPO will monitor the Project’s execution and adherence to the plan as the Project progresses. • The October 2025 strategy to deliver the Project is being revised based on poor project performance. • The revised strategy should be analyzed using the approved Change Control Process for any impact to project scope. |
| Resources |
• The Project is working to obtain an additional program resource to assist with Organization Change Management (OCM) responsibilities. • Considering the lack of deliverable quality, the vendors staff may not have the required skillset to deliver the Project. |
| Quality |
• IV&V is providing a monthly report and attending project meetings. • IPO has witnessed IV&V providing analysis and recommendations in the team meetings and monthly reports. • The Project Management Plan contains a subsidiary Quality Management Plan that adequately describes the quality expectations of the Project. • IPO has witnessed vendor deliverables content and quality not meeting expectations. |
| Risk And Issues |
• The Project has an acceptable Risk Management Plan. • The Project is using a Risk Issue Decision log for tracking, and the topics are discussed in the Bi-Weekly Status meetings and the ESC. • The risk and issue register was not updated for the months of March, April and May 2026 as the Project Team works to meet the requirements to lift the pause. |
| Transition Readiness |
• The Project has requested an additional program resource to act as an ERP Ambassador and support OCM communications. |
| Conditions For Approval |
• A Special Project Report (SPR) is required pursuant to the State Administrative Manual section 4945. |
| Corrective Action |
• There are no corrective action plans in place. |