The California Department of Food and Agriculture, Animal Health and Food Safety Services (AHFSS) Division, is proposing to replace their existing Emerging Threats system to correct and eliminate multiple deficiencies that have arisen over the maintenance and operations life cycle of the system and to provide an enterprise-wide solution for all programs within the AHFSS Division.
| Agency / State Entity | General Government / Food and Agriculture, Department of |
|---|---|
| Total Cost | $50,178,609 |
| Last Approved Start Date | 12/04/2025 |
| Last Approved Finish Date | 12/29/2028 |
| Criticality Rating | High |
| IPOR Reporting Period | Overall IPOR Rating |
|---|---|
| 04/01/2026 - 04/30/2026 |
Key Questions
Is the project on track to satisfy the customer's business objectives?Yes
Is the project on track to achieve the objectives in the approved timeframe?Yes
Is the project on track to achieve the objectives within the approved budget?Yes
| Project Overall Health | Comments |
|---|---|
| During the April 2026 reporting period, the ET2 project status remained Green. The Project Team is progressing well with two parallel efforts Release 1 and Release 2. • Release 1 (Payment Gateway Interim Solution) Sprint 2 is on track and scheduled to be completed by 8 May 2026. • Release 2 (Core Data) Sprint 2 is scheduled to be completed by 12 May 2026. • IPO noted that all the scheduled tasks are on track and do not have any concerns at this time. |
| Focus Area/Rating | Comments |
|---|---|
| Governance |
During the reporting period of April 2026, the ET2 project status continues to be Green. • The Executive Steering Committee meeting was held on 4/2/26 with good participation. • The Project Team, IV&V, and IPO provided project status and assessments respectively. • The CDT Oversight team does not have any concerns at this time. |
| Time Management |
During the reporting period of April 2026, the ET2 Time Management Focus Area status remains Green as the Project Team continues to perform according to the published Integrated Master Project Schedule. • The Integrated Master Schedule was baselined and is maintained on a regular cadence. While the detailed tasks are being updated, there is no change to the project milestones. • The Project team continues to work on Release 1 Sprint 2 focused on the Payment Gateway Interim Solution Release 1 (Payment Gateway Interim Solution). The expected date of completion for Sprint 2 is 8 May 2026. • The Project Team completed Release 2 (Core Data) Sprint 1 and is currently working on Sprint 2 with estimated completion by 12 May 2026. • IPO noted the Project’s execution is on plan according to the Master Project Schedule and has no concerns at this point. |
| Cost & Contract Management |
The ET2 Cost and Contract Management Focus Area remains Green during the reporting period of April 2026 as the project cost continues to remain under the approved budget. • The project cost incurred in the month of April was $1,576,906 out of the total project cost of $50,178,609. • IPO will continue to monitor the Project’s execution and adherence to cost and contract management plans as the Project progresses. |
| Scope Management |
During the reporting period of April 2026, the ET2 project’s Scope Management Focus Area status remains Green as The Project Team continues work on the approved scope. • IPO will monitor the Project’s execution and adherence to the Scope Management Plan as the Project progresses. |
| Resources |
The ET2 Resources Focus Area status remains Green as the Project is fully staffed, and no positions remain vacant. • At the recommendation of IPO, the Project Management Office added one project manager to assist the project director. • IPO has no concerns at this point. |
| Quality |
During the reporting period of April 2026, the ET2 Project Quality Management Focus area remains Green as the Project Team continues with the implementation of the system. • The Project Team is finalizing ET2 Project - Master Test Plan, which will incorporate all the activities performed by System Integrator (SI), Quality Assurance (QA)/Control Team, and User Acceptance Testing (UAT) teams. • IPO will monitor the Project’s execution and adherence to the Quality Management Plan as the Project progresses, |
| Risk And Issues |
• The Project Team did not identify any new risks or issues related to the project. • The IPO does not have any concerns at this point. |
| Transition Readiness |
The Project is in the Design, Development and Deployment stage, and it is too early to evaluate the transition readiness of the organization. |
| Conditions For Approval |
• Within 90 calendar days after November 21, 2025, Approval Letter, which was February 21, 2026, the CDFA shall develop and submit to the CDT an Integrated Master Project Schedule that incorporates both State and System Integrator (SI) deliverables, milestones, and activities. The schedule shall reflect a clearly defined and logical critical path and adhere to the Project Management Institute (PMI) Schedule Management best practices and California Project Management Framework (CA-PMF) standards. The schedule shall be developed and maintained using Microsoft Project. • No later than 60 calendar days prior to the initiation of testing activities by the SI, the CDFA shall submit the approved ET2 Project Test Management Plan to the CDT. With concurrence by IPO, the Integrated Master Project Schedule was submitted to the CDT for review on 3/13/26 and the draft ET2 Test Management Plan was submitted to the CDT for review on 3/18/26. The CDT provided comments and feedback on both with no major concerns identified with either. The Project indicated that CDT comments on the draft Test Management Plan are being incorporated into the final version. Both conditions in the ET2 Project Approval have been satisfactorily met. |
| Corrective Action |
• There are no corrective action plans in place. |