Independent Project Oversight Report (IPOR) Rating

3600-079 Wireless Digital Evidence Management System for ICCS (ICCS)

Testing, acquisition and deployment of 400 units of Body Worn and 400 units of In-car Camera System for The California Department of Fish and Wildlife’s Law Enforcement Division (LED). The use of body-worn and vehicle cameras has made law enforcement agencies more transparent and accountable to the public and has helped agencies evaluate and officer professionalism and training needs.

Project Details

Agency / State Entity Natural Resources / Fish and Wildlife, Department of
Total Cost $7,107,050
Last Approved Start Date 07/21/2023
Last Approved Finish Date 12/06/2025
Criticality Rating Medium
IPOR Reporting Period Overall IPOR Rating
01/01/2026 - 01/31/2026
Green
Independent Project Oversight Dashboard

Key Questions

Is the project on track to satisfy the customer's business objectives?Yes

Is the project on track to achieve the objectives in the approved timeframe?Yes

Is the project on track to achieve the objectives within the approved budget?Yes

Project Overall Health Comments
Green
• The Project Team has finalized the M&O Plan and completed all Project Close-out activities. • The Project Team will be working on the Post Implementation and Evaluation Report (PIER) that is due to the CDT on June 6, 2027.
Focus Area/Rating Comments
Governance

green icon Green
• The Project has entered the Closing Phase, the ESC Meeting series was canceled with the last meeting being held in September 2025.
Time Management

green icon Green
• The Project completed 1.5 months beyond the approved baseline end date.
Cost & Contract Management

green icon Green
• The project contract expenditures were lower than budgeted because DFW camera needs were reduced.
Scope Management

yellow icon Yellow
• A high-level Decision Log incorporated into the Risk and Issue Log was used to track decisions and changes. • IPO observed that the formal Change Request documentation and analysis process as outlined in the Project Management Plan was not followed.
Resources

green icon Green
• IPO observed delays in reviewing the M&O Plan due to DFW staff availability.
Quality

green icon Green
• IPO observed quality improvements in the vendor’s deliverables towards the last half of the project.
Risk And Issues

green icon Green
• IPO observed the Risk and Issue Log being updated on a regular basis throughout the project.
Transition Readiness

green icon Green
• DFW is currently executing the Organizational Change Management (OCM) Plan. • The Project has completed Project Close-out Activities and has entered the M&O Phase.
Conditions For Approval

green icon Green
• There are no conditions for approval in place
Corrective Action

green icon Green
• There are no corrective action plans in place.