7350-094 CalOSHA Data Management System (CalOSHA DMS)
DIR proposes to acquire an integrated online system for its Division of Occupational Safety and Health (DOSH), better known as “Cal/OSHA”. The new system will support customizable workflow and reporting, more readily adapt to business needs and provide better management of the data flowing between Cal/OSHA and the Federal OSHA Information System (OIS).
Project Details
| Agency / State Entity | Labor and Workforce Development / Industrial Relations, Department of |
|---|---|
| Total Cost | $99,993,483 |
| Last Approved Start Date | 06/27/2024 |
| Last Approved Finish Date | 10/31/2027 |
| Criticality Rating | Medium |
| IPOR Reporting Period | Overall IPOR Rating |
|---|---|
| 10/01/2026 - 10/31/2026 |
Independent Project Oversight Dashboard
Key Questions
Is the project on track to satisfy the customer's business objectives?Yes
Is the project on track to achieve the objectives in the approved timeframe?Uncertain
Is the project on track to achieve the objectives within the approved budget?Uncertain
| Project Overall Health | Comments |
|---|---|
| The project’s overall health rating continues to remain escalated. • The IPO Manager observed that project activities remain aligned with approved business objectives. The schedule rebaselining remains pending SPR 1 approval. • The project continues to align with approved business objectives. However, the project schedule has not yet been rebaselined pending SPR approval, limiting the ability to assess performance against an approved schedule baseline. Data integration and migration defects, unresolved user acceptance testing defects, and continuing scope and quality challenges remain areas of concern and may affect release execution if not resolved timely. Consultation UAT was completed in accordance with the current project plan, while Enforcement approvals and demonstration activities continued to progress behind schedule. |
| Focus Area/Rating | Comments |
|---|---|
| Governance |
The Governance Management focus area continues to remain in satisfactory status because: • The Cal/OSHA project team follows the processes outlined in the governance processes, defined decision-making structures, and continued executive engagement; however, execution of identified corrective actions remains pending. |
| Time Management |
The Time Management focus area rating continues to remain in escalated status because: • The IPO Manager reviewed the Project Schedule for the planned Go Live dates for Release 1 and Release 2 which remain unchanged and currently SPR 1 is being reviewed by the department to rebaseline Release 3 schedule. • Consultation UAT completed on October 30, 2026. Enforcement deferred demonstrations due November 6, 2026, and Enforcement SIT due to start November 9, 2026, are at risk. • The current schedule has not established a validated critical path, does not fully reflect state resource assignments, and remains pending rebaselining, limiting the project's ability to accurately measure schedule performance. |
| Cost & Contract Management |
The Cost & Contract Management focus area is in satisfactory status because: • The IPO Manager observed that project remains with no unplanned cost impacts identified in the October 2026 reporting period. • Data Migration vendor procurement activities and GCP platform implementation activities continue to warrant monitoring to assess potential future budget and schedule impacts. • SPR 1 is being reviewed by DIR to rebaseline the release schedule. |
| Scope Management |
The Scope Management focus area continues to remain in escalated status because: • The IPO Manager observed daily stand-up meetings and noted scope remains substantially stable. Enforcement and Consultation user stories continued to progress more slowly than planned. • Scope remains substantially stable at the release level, but story-level progress lags. • The project reported 59 Consultation stories pending approval, approximately 90 deferred Enforcement stories, and 110 reporting stories pending approval at the end of the reporting period, indicating continued backlog management and scope completion challenges. SPR approval must confirm the revised scope boundaries. |
| Resources |
The Resource Management focus area rating remained in satisfactory status because: • The IPO Manager observed the project report State staffing remains generally stable. The project filled six of seven Program positions and 19 of 22 IT positions and continues to recruit for the remaining vacancies. |
| Quality |
The Quality Management focus area rating continues to remain in escalated status because: • The IPO Manager observed in daily project meetings that project reported more than 300 UAT defects, 69 open UAT defects and 1,127 code quality gaps, including 222 high-severity gaps and 700 medium-severity gaps. Enforcement sprint quality remained inconsistent during the reporting period, increasing the risk of additional rework and schedule impacts. |
| Risk And Issues |
The Risks and Issue Management area rating remained in cautionary status because: • The IPO Manager observed in daily project meetings that the project raised one new significant risk, closed six risks and escalated one risk to an issue. It raised one new significant issue, CDP-3468, and closed three issues. FedOIS schema changes and GCP ingestion readiness remain active risks with the potential to affect implementation timelines and increase project rework. |
| Transition Readiness |
The Transition Readiness focus area rating remained satisfactory because: • The IPO Manager observed in daily project meeting that Consultation UAT completed on October 30, 2026. Training, deployment preparation and cutover planning activities remain aligned with current implementation milestones; however, readiness remains dependent upon closure of outstanding defects and completion of code freeze activities. |
| Conditions For Approval |
All Conditions of Approval have been met. |
| Corrective Action |
N/A |