Independent Project Oversight Report (IPOR) Rating
-
- Satisfactory, no corrective action necessary.
-
- Caution, risks/issues exist. There may be a need for corrective action in the near future.
-
- Escalated for immediate corrective action. There is a significant risk to the health of the project.
-
- Not enough data is available to make a determination about the project health.
-
No Report Available - Indicates that a Report is not available for publishing for the reporting period.
8950-059 CalVet Electronic Health Record (CEHR)
The California Department of Veterans Affairs proposes to replace the existing Veteran Home’s electronic health records system.
Project Details
| Agency / State Entity | General Government / Veterans Affairs, Department of |
|---|---|
| Total Cost | $39,067,807 |
| Last Approved Start Date | 03/09/2020 |
| Last Approved Finish Date | 10/16/2026 |
| Criticality Rating | Medium |
| IPOR Reporting Period | Overall IPOR Rating |
|---|---|
| 09/01/2026 - 09/30/2026 |
Independent Project Oversight Dashboard
Key Questions
Is the project on track to satisfy the customer's business objectives?Yes
Is the project on track to achieve the objectives in the approved timeframe?Yes
Is the project on track to achieve the objectives within the approved budget?Yes
| Project Overall Health | Comments |
|---|---|
| The CEHR Project is rated Satisfactory (GREEN). Overall, the project is in alignment with the project’s schedule and costs to the approved SPR 3 timeline and budget baselines. |
| Focus Area/Rating | Comments |
|---|---|
| Governance |
This focus area is rated Escalated for Immediate Corrective Action (Red). • Governance Plan update (v5.0) to align Roles and Responsibilities to current leadership practices has had no forward movement for months. Assigned roles and responsibilities remain inconsistent with Governance Plan (v4.0) plan in effect. • Project Status Report (PSR) for August and September 2026 were submitted late (September 12, 2026). |
| Time Management |
This focus area is rated as Satisfactory (Green). • Project end date is “On Schedule” per the CDT approved SPR3 baseline for Certificate of Delivery. • Schedule Management Plan (v7.0) is in effect and management practices are being executed in accordance with the documented approach. |
| Cost & Contract Management |
This focus area is rated Satisfactory (Green). • Project expenditures align to date with the Financial Analysis Worksheets (FAW) of the approved SPR 3 baseline. • Cost Management Plan (v3.0) is in effect. • Contract Management Plan (v6.0) is in effect. Deliverable reviews follow a defined process and acceptance is formally documented prior to invoices being paid. |
| Scope Management |
This focus area is rated Cautionary (Yellow). • Scope Management Plan (v6.0) is in effect. • The increasing number of change requests since December 2025 indicate shifting requirements or the need to clarify, add or remove scope. • Scope verification (internal check for accuracy and completeness) has been inconsistent over the life of the project impacting Scope validation (formal, external approval that deliverables and business needs have been met) essential to the Certificate of Delivery deliverable. |
| Resources |
This focus area is rated Cautionary (Yellow). • The transition to M&O support has revealed an increased need for IT support staff to fulfill critical roles currently provided by CEHR project team members. • Availability of Policy and Compliance (P&C) resources has hindered UAT closeout and Change Request (CR) progress impacting CEHR adoption across Homes. |
| Quality |
This focus area is rated Cautionary (Yellow). • Quality Management Plan (v7.0) is in effect. • Quality Control (QC) has inconsistencies over the life of the project that created QA/QC rework in order to confidently attain Certificate of Delivery. CEHR Testing team continues to catch up on Quality Planning documentation standards to establish a framework for QA/QC in M&O moving forward. |
| Risk And Issues |
This focus area is Satisfactory (Green). • An updated Risk/Issue Management Plan (v8.0) remains in progress. • Appropriate team members are involved in identifying, analyzing, and mitigating risks and active issues. |
| Transition Readiness |
This focus area is rated Satisfactory (Green). • OCM Plan (v5.0) is in effect. • End User/Stakeholder communications are executed appropriately with clear communication that all issues and requests must now transition to the CalVet Help Desk ticketing process. |
| Conditions For Approval |
No conditions for approval. |
| Corrective Action |
No corrective action plans are required at this time. |