Independent Project Oversight Report (IPOR) Rating

Back to Listing

8950-059 CalVet Electronic Health Record (CEHR)

The California Department of Veterans Affairs proposes to replace the existing Veteran Home’s electronic health records system.

Project Details

Agency / State Entity General Government / Veterans Affairs, Department of
Total Cost $39,067,807
Last Approved Start Date 03/09/2020
Last Approved Finish Date 10/16/2026
Criticality Rating Medium
IPOR Reporting Period Overall IPOR Rating
09/01/2026 - 09/30/2026
Green
Independent Project Oversight Dashboard

Key Questions

Is the project on track to satisfy the customer's business objectives?Yes

Is the project on track to achieve the objectives in the approved timeframe?Yes

Is the project on track to achieve the objectives within the approved budget?Yes

Project Overall Health Comments
Green
The CEHR Project is rated Satisfactory (GREEN). Overall, the project is in alignment with the project’s schedule and costs to the approved SPR 3 timeline and budget baselines.
Focus Area/Rating Comments
Governance

Red
This focus area is rated Escalated for Immediate Corrective Action (Red). • Governance Plan update (v5.0) to align Roles and Responsibilities to current leadership practices has had no forward movement for months. Assigned roles and responsibilities remain inconsistent with Governance Plan (v4.0) plan in effect. • Project Status Report (PSR) for August and September 2026 were submitted late (September 12, 2026).
Time Management

Green
This focus area is rated as Satisfactory (Green). • Project end date is “On Schedule” per the CDT approved SPR3 baseline for Certificate of Delivery. • Schedule Management Plan (v7.0) is in effect and management practices are being executed in accordance with the documented approach.
Cost & Contract Management

Green
This focus area is rated Satisfactory (Green). • Project expenditures align to date with the Financial Analysis Worksheets (FAW) of the approved SPR 3 baseline. • Cost Management Plan (v3.0) is in effect. • Contract Management Plan (v6.0) is in effect. Deliverable reviews follow a defined process and acceptance is formally documented prior to invoices being paid.
Scope Management

Yellow
This focus area is rated Cautionary (Yellow). • Scope Management Plan (v6.0) is in effect. • The increasing number of change requests since December 2025 indicate shifting requirements or the need to clarify, add or remove scope. • Scope verification (internal check for accuracy and completeness) has been inconsistent over the life of the project impacting Scope validation (formal, external approval that deliverables and business needs have been met) essential to the Certificate of Delivery deliverable.
Resources

Yellow
This focus area is rated Cautionary (Yellow). • The transition to M&O support has revealed an increased need for IT support staff to fulfill critical roles currently provided by CEHR project team members. • Availability of Policy and Compliance (P&C) resources has hindered UAT closeout and Change Request (CR) progress impacting CEHR adoption across Homes.
Quality

Yellow
This focus area is rated Cautionary (Yellow). • Quality Management Plan (v7.0) is in effect. • Quality Control (QC) has inconsistencies over the life of the project that created QA/QC rework in order to confidently attain Certificate of Delivery. CEHR Testing team continues to catch up on Quality Planning documentation standards to establish a framework for QA/QC in M&O moving forward.
Risk And Issues

Green
This focus area is Satisfactory (Green). • An updated Risk/Issue Management Plan (v8.0) remains in progress. • Appropriate team members are involved in identifying, analyzing, and mitigating risks and active issues.
Transition Readiness

Green
This focus area is rated Satisfactory (Green). • OCM Plan (v5.0) is in effect. • End User/Stakeholder communications are executed appropriately with clear communication that all issues and requests must now transition to the CalVet Help Desk ticketing process.
Conditions For Approval

Green
No conditions for approval.
Corrective Action

Green
No corrective action plans are required at this time.
Project Approval Documents