The California Department of Corrections and Rehabilitation (CDCR), an augmentation to the General Fund of $8.1 million in 2023-24, $9.0 million in 2024-25 and $7.5 million in 2025-26 to move CDCR’s current Enterprise Resource Platform system (ERP), SAP/Business Information System (BIS) to SAP’s new ERP system/platform offering called S4 HANA. The requested funding includes all the normal phases required during a system migration: Blueprinting, Unit Testing, Integration Testing, Training, Cutover Processes and Post Go Live Support.
| Agency / State Entity | Corrections and Rehabilitation / Corrections and Rehabilitation, Department of |
|---|---|
| Total Cost | $68,289,406 |
| Last Approved Start Date | 06/28/2024 |
| Last Approved Finish Date | 09/25/2026 |
| Criticality Rating | High |
| IPOR Reporting Period | Overall IPOR Rating |
|---|---|
| 04/01/2026 - 04/30/2026 |
Key Questions
Is the project on track to satisfy the customer's business objectives?Yes
Is the project on track to achieve the objectives in the approved timeframe?Yes
Is the project on track to achieve the objectives within the approved budget?Yes
| Project Overall Health | Comments |
|---|---|
| The overall health of the project is Green, as the project is progressing according to timeline. Budget and scope are in alignment with approved baseline. |
| Focus Area/Rating | Comments |
|---|---|
| Governance |
• Project roles and responsibilities are established and documented. • Executive Steering Committee (ESC) meeting was held on April 22, 2026, and was well attended. • Decisions are being made timely and at the right levels. • Governance Management Plan is in place and processes are being followed. |
| Time Management |
• Project activities are progressing in accordance with the approved timeline. • Six (6) of thirteen (13) SAP Ariba milestones were completed on time. • Schedule Management Plan is in place and processes are being followed. |
| Cost & Contract Management |
• Current project costs are in alignment with approved budget. • Contract and Cost Management Plans are in place and processes are being followed. |
| Scope Management |
• Scope is in alignment with the approved baseline. • Project deployed three (3) of the six (6) early release Business Process Transformations (BPTs) during the reporting period. • No change to project scope during this reporting period. • No change requests (CRs) were approved. • Scope and Requirements Management Plans are in place and processes are being followed. |
| Resources |
• Project team appears to be working well together. • Resources have the tools necessary to complete tasks as assigned. • Resource Management Plan is in place and processes are being followed. |
| Quality |
• Presentations and demos created and delivered by the contractor have been clean, neat, and well organized. • Functional Unit Testing (FUT) continued during the reporting period. • One (1) deliverable was submitted and two (2) were approved during the reporting period. • Quality Management Plan is in place and processes are being followed. |
| Risk And Issues |
• Risk and issues are being identified and tracked. • Project Riks/Issue bi-weekly meetings were held during the reporting period. • Risk and Issue Management Plans are in place. |
| Transition Readiness |
• Organization Change Management (OCM) is appropriate for this stage of the project. • First Change Readiness Assessment (CRA) survey results were submitted during the reporting period. |
| Conditions For Approval |
• The condition of providing updated project management plans from PAL within 90 days of contract start and an updated Master Project Schedule within 60 days of contract start has been satisfied. |
| Corrective Action |
• There are no corrective action plans in place. |