Independent Project Oversight Report (IPOR) Rating

Back to Listing

3600-081 Environmental Review and Permitting Project (ERPP)

The California Department of Fish and Wildlife (CDFW) proposes to update the statewide online permitting systems, Environmental Permit Information Management System (EPIMS) and Scientific Collecting Permit Portal (SCPP). The scope will also include improving operational efficiency in management of environmental permits by supporting other critical Environmental Review processes including online application and tracking of California Endangered Species Act (CESA) Take Permits whose tracking platform known as Project Tracking is no longer supported. The goal of this project is to create one system that can incorporate these systems.

Project Details

Agency / State Entity Natural Resources / Fish and Wildlife, Department of
Total Cost $13,317,754
Last Approved Start Date 01/07/2025
Last Approved Finish Date 01/06/2027
Criticality Rating Medium
IPOR Reporting Period Overall IPOR Rating
09/01/2026 - 09/30/2026
Red
Independent Project Oversight Dashboard

Key Questions

Is the project on track to satisfy the customer's business objectives?Uncertain

Is the project on track to achieve the objectives in the approved timeframe?No

Is the project on track to achieve the objectives within the approved budget?Uncertain

Project Overall Health Comments
Red
• As of September, the project pause that was initiated in January 2026 remains in effect until the vendor can deliver a realistic path forward. • Of the twenty-six tasks that need to be completed to lift the pause, one remains to be completed i.e. an updated schedule. • Once a realistic revised schedule is identified, the DFW will work to gain DFW executive approval, per the Project’s governance process and complete a SPR to submit to the CDT. • In September 2026, Sprint Goal: Permit #1 ITP Online Form, Global Search Functionality, Permit Wizard, Global Payment GUI screens was completed.
Focus Area/Rating Comments
Governance

Yellow
• A Governance Structure has been agreed to and documented in the project planning process. • The Executive Steering Committee meeting was well attended by all stakeholders and DFW leadership. • The yellow rating is a result of an unknow date that a draft of the SPR will be provided to the CDT.
Time Management

Red
• The Project has an acceptable Schedule Management Plan. • Discovery activities for Permit #2 and #3 on hold until schedule is approved completed. • An updated project schedule has been delivered to DFW last month and continues to be refined. • The Project is now in the twenty-first month of execution and has not updated the Project schedule.
Cost & Contract Management

Green
• The Project has an acceptable Cost Management Plan and Contract Management Plan. • IPO has witnessed the Project executing and adhering to the Cost and Contract Management Plans.
Scope Management

Yellow
• The Project has an acceptable Scope Management Plan. • IPO will monitor the Project’s execution and adherence to the plan as the Project progresses. • The revised strategy should be analyzed using the approved Change Control Process for any impact to project scope.
Resources

Green
• Project management tasks and work are being completed within quality expectations and the approved budget.
Quality

Red
• IV&V is providing a monthly report and attending project meetings. • IPO has witnessed IV&V providing analysis and recommendations in the team meetings and monthly reports along with the Project embracing several recommendations. • The Project Management Plan contains a subsidiary Quality Management Plan that adequately describes the quality expectations of the Project. • Once all the pause conditions are met, this focus area can begin to transition towards green.
Risk And Issues

Yellow
• The Project has an acceptable Risk Management Plan. • The Project is using a Risk Issue Decision log for tracking and reporting status to Project stakeholders. • Risks and issues are not being discussed on a reoccurring basis in an open forum.
Transition Readiness

Green
• The Project has sufficient resources to support the Organizational Change Management (OCM) Plan and manage the change communications for the Project.
Conditions For Approval

Yellow
• A Special Project Report (SPR) is required pursuant to the State Administrative Manual section 4945.
Corrective Action

Green
• There are no corrective action plans in place.