The California Department of Food and Agriculture, Animal Health and Food Safety Services (AHFSS) Division, is proposing to replace their existing Emerging Threats system to correct and eliminate multiple deficiencies that have arisen over the maintenance and operations life cycle of the system and to provide an enterprise-wide solution for all programs within the AHFSS Division.
| Agency / State Entity | General Government / Food and Agriculture, Department of |
|---|---|
| Total Cost | $50,178,609 |
| Last Approved Start Date | 12/04/2025 |
| Last Approved Finish Date | 12/29/2028 |
| Criticality Rating | High |
| IPOR Reporting Period | Overall IPOR Rating |
|---|---|
| 03/01/2026 - 03/31/2026 |
Key Questions
Is the project on track to satisfy the customer's business objectives?Yes
Is the project on track to achieve the objectives in the approved timeframe?Yes
Is the project on track to achieve the objectives within the approved budget?Yes
| Project Overall Health | Comments |
|---|---|
| During the March 2026 reporting period, the ET2 project status remained Green. The Project Team completed the Requirements Validation and Discovery sessions and began design and development activities for Release 1. • The Project Team completed Requirements Validation and Discovery sessions with the Subject Matter Experts (SMEs). • The Project Team submitted the Integrated Master Project Schedule within 90 days after issuance of the S4PRA Approval Letter as required by the condition in the CDT Approval Letter (see page 4 of this document for more detail). • The CDT Oversight management reviewed and approved the Integrated Master Project Schedule. The Oversight management noted that all the scheduled tasks are on track and do not have any concerns at this time. |
| Focus Area/Rating | Comments |
|---|---|
| Governance |
During the reporting period of March 2026, the ET2 project status continues to be Green. The Project Team held its first Executive Steering Committee (ESC) meeting during the month. • The first Executive Steering Committee meeting was held on 3/5/26 with good participation. • The CDT Oversight team does not have any concerns at this time. |
| Time Management |
During the reporting period of March 2026, the ET2 project status remains Green as the Project Team continues to perform according to the published Integrated Master Project Schedule. • The Integrated Master Project Schedule was approved by the CDT Oversight management and the condition in Approval Letter is satisfied. •The Project team began working on Release 1, Sprint 1 focused on the Payment Gateway Interim Solution Release 1. • IPO will monitor the Project’s execution and adherence to the Master Project Schedule as the project progresses. |
| Cost & Contract Management |
The ET2 project status remains Green during the reporting period of March 2026 as the Project Team as the project cost continues to remain under the approved budget. • The project cost incurred in the month of March was $1,476,743 out of the total project cost of $50,178,609. • IPO will continue to monitor the Project’s execution and adherence to cost and contract management plans as the Project progresses. |
| Scope Management |
During the reporting period of March 2026, the ET2 project status remains Green as the project team wraps up the Requirements Validation and Discovery sessions with the SMEs. • Requirements Validation and Discovery sessions have not identified any change in the scope of project. • IPO will monitor the Project’s execution and adherence to the Scope Management Plan as the Project progresses. |
| Resources |
ET2 project status remains Green as the Project is fully staffed, and no positions remain vacant. |
| Quality |
During the reporting period of March 2026, the ET2 Project status remains Green as the Project Team began Design, Development, and Deployment for Release 1. • The draft QA Test Management Plan for Release 1 was submitted to CDT on 3/18/26 for review in compliance with the condition in the CDT ET2 Project Approval Letter. The CDT provided comments and feedback on the Plan to the Project on April 1, 2026. • The Independent Verification and Validation (IV & V) will start publishing monthly IV&V reports beginning in April 2026. • IPO will monitor the Project’s execution and adherence to the Quality Management Plan as the Project progresses, |
| Risk And Issues |
• The Project Team has begun using a Risk and Issue Log to track risks and issues identified. • The CDT Oversight Management do not have any concerns at this point. |
| Transition Readiness |
The Project is in the Design, Development and Deployment stage, and it is too early to evaluate the transition readiness of the organization. |
| Conditions For Approval |
• Within 90 calendar days after November 21, 2025, Approval Letter, which was February 21, 2026, the CDFA shall develop and submit to the CDT an Integrated Master Project Schedule that incorporates both State and System Integrator (SI) deliverables, milestones, and activities. The schedule shall reflect a clearly defined and logical critical path and adhere to the Project Management Institute (PMI) Schedule Management best practices and California Project Management Framework (CA-PMF) standards. The schedule shall be developed and maintained using Microsoft Project. • No later than 60 calendar days prior to the initiation of testing activities by the SI, the CDFA shall submit the approved ET2 Project Test Management Plan to the CDT. With concurrence by IPO, the Integrated Master Project Schedule was submitted to the CDT for review on 3/13/26 and the draft ET2 Test Management Plan was submitted to the CDT for review on 3/18/26. The CDT provided comments and feedback on both with no major concerns identified with either. The Project indicated that CDT comments on the draft Test Management Plan are being incorporated into the final version. Both conditions in the ET2 Project Approval have been satisfactorily met. |
| Corrective Action |
• There are no corrective action plans in place. |
20250626 Release-16