Independent Project Oversight Report (IPOR) Rating

2660-545 Transportation System Network Replacement (TSNR)

The California Department of Transportation (Caltrans) proposes to implement a new Transportation System Network (TSN) solution that integrates geospatial information required by MAP-21 and the FAST Act and addresses current system performance deficiencies.

Project Details

Agency / State Entity Transportation / Transportation, Department of
Total Cost $34,038,238
Last Approved Start Date 04/07/2022
Last Approved Finish Date 10/24/2025
Criticality Rating High
IPOR Reporting Period Overall IPOR Rating
11/01/2025 - 11/30/2025
Green
Independent Project Oversight Dashboard

Key Questions

Is the project on track to satisfy the customer's business objectives?Yes

Is the project on track to achieve the objectives in the approved timeframe?No

Is the project on track to achieve the objectives within the approved budget?Yes

Project Overall Health Comments
Green
During the November reporting period, overall project health remained Green. The project continued to progress toward the Executive Steering Committee (ESC) approved December 2025 Go-Live, with final User Acceptance Testing (UAT), data migration preparation, and system administration training underway. All focus areas remained stable, and no new risks, issues, or variances were introduced. Schedule monitoring continues due to UAT sequencing, but it has not impacted the Go-Live timeline.
Focus Area/Rating Comments
Governance

green icon Green
Governance remained Green. Regular leadership, oversight, and project management meetings continued to provide visibility into system readiness, module completion, and Go-Live preparation activities.
Time Management

green icon Green
Time Management shifted from Yellow to Green this period and is trending to stay so until project closeout. The project maintained steady progress against the ESC approved December 2025 Go-Live date. All modules advanced through final UAT, data migration preparation, and administration training. No schedule delays or milestone changes were reported, and UAT monitoring continues to ensure timely completion.
Cost & Contract Management

green icon Green
Cost and Contract Management remained Green. Expenditures remained on track, with approximately $21.2 million spent of the $32.3 million budget, representing about 66% of the total budget. All vendor contracts, including Systems Integrator (SI), Organizational Change Management (OCM), and Independent Validation and Verification (IV&V), remained active and performing within scope. No new financial risks, amendments, or contract issues were identified.
Scope Management

green icon Green
Scope Management maintained its Green rating. All November activities were completed within the approved SPR #1 scope, and the change freeze remained in place through Go-Live. No new scope requests, deferrals, or modifications were introduced.
Resources

green icon Green
Resource Management remained Green. Staffing levels across Caltrans and vendor partners continued to support final UAT, documentation, training, and acceptance activities. No resource shortages or skill gaps were observed.
Quality

green icon Green
Quality Management remained Green. Testing for all modules continued with stable results and no major defects identified. UAT, data validation, and documentation reviews remained consistent with the Quality Management Plan. IV&V and SQM oversight confirmed adherence to quality standards.
Risk And Issues

green icon Green
Risks and Issues Management remained Green. One high-severity risk related to potential UAT overruns remains under active mitigation, but has not impacted the schedule. One open issue related to ArcGIS Pro database connectivity remained under ESRI Premium Support review. No new risks or issues were reported.
Transition Readiness

green icon Green
Transition Readiness remained Green. Final training, UAT completion, documentation updates, and data migration preparation continued as scheduled. Activities remain aligned with the December 2025 Go-Live timeline with no new readiness concerns identified.
Conditions For Approval

green icon Green
All conditions for approval have been satisfied.
Corrective Action

green icon Green
No corrective actions were identified during the November reporting period.