California Department of Fish and Wildlife (CDFW) proposes to build and maintain a new Master Observation Database System (MODS) that will provide the California Natural Diversity Database (CNDDB) program with the ability to capture, store, enable updates to, and retrieval and usage of, and preserve, all special status species observation data; including all details, as/however received or input, in/as individual records, in a single database repository.
| Agency / State Entity | Natural Resources / Fish and Wildlife, Department of |
|---|---|
| Total Cost | $14,116,832 |
| Last Approved Start Date | 06/12/2025 |
| Last Approved Finish Date | 03/22/2028 |
| Criticality Rating | High |
| IPOR Reporting Period | Overall IPOR Rating |
|---|---|
| 05/01/2026 - 05/31/2026 |
Key Questions
Is the project on track to satisfy the customer's business objectives?Yes
Is the project on track to achieve the objectives in the approved timeframe?Yes
Is the project on track to achieve the objectives within the approved budget?Yes
| Project Overall Health | Comments |
|---|---|
| • A updated Project Schedule has been approved in May 2026 that delivers the project within the approved end date. • Sprint 1 development has begun. |
| Focus Area/Rating | Comments |
|---|---|
| Governance |
• Independent Project Oversight (IPO) has observed the May 2026 Executive Steering Committee (ESC) reporting structure, that includes reporting on open risks and issues and the impact to the schedule operating as planned. • IPO has found that the structure and the content provided in the ESC is appropriate for the audience. |
| Time Management |
• The Project has an acceptable Schedule Management Plan. • The Project has approved a revised Schedule that delivers the Project ahead of the approved end date. |
| Cost & Contract Management |
• The Project has an acceptable Cost Management Plan and Contract Management Plan. • Actual staff costs are being reported monthly in arrears and vendor invoices have begun being paid. |
| Scope Management |
• The Project has acceptable Scope, Requirements and Change Control Management Plans in place. • Project making seven decisions in May 2026. |
| Resources |
• The project is reporting it has sufficient resources to deliver objectives within the approved end date. • The Project has an acceptable Resource Management Plan. |
| Quality |
• Independent Verification and Validation (IV&V) is attending project meetings and conducting a 1:1 monthly review meeting with DFW and IPO. • IV&V is reviewing and providing feedback on the vendors deliverables, as well as other project artifacts to ensure they are in line with best practices and industry standards. • The Project has an acceptable Quality Management Plan. |
| Risk And Issues |
• The Project has an acceptable Risk Management Plan. • The Project Team is tracking risks and issues in a log and keeping statues up to date. |
| Transition Readiness |
• The Project has an acceptable Organizational Change Management Plan. |
| Conditions For Approval |
• There are no conditions for approval in place. |
| Corrective Action |
• There are no corrective action plans in place. |