Independent Project Oversight Report (IPOR) Rating

Back to Listing

7100-234 California Job Opening Browse System Modernization (CalJOBS)

The Employment Development Department (EDD) Workforce Services Branch (WSB), a department within the Labor and Workforce Development Agency (LWDA), proposes to modernize CalJOBS to make the system more user-friendly for all stakeholders, more customizable to the department’s needs, and include robust reporting features to meet the needs of system users. The modernization effort will enable the system to better facilitate the administration and reporting requirements for state and federal programs.

Project Details

Agency / State Entity Labor and Workforce Development / Employment Development Department
Total Cost $53,887,116
Last Approved Start Date 09/08/2025
Last Approved Finish Date 08/31/2028
Criticality Rating Medium
IPOR Reporting Period Overall IPOR Rating
10/01/2026 - 10/31/2026
Yellow
Independent Project Oversight Dashboard

Key Questions

Is the project on track to satisfy the customer's business objectives?Yes

Is the project on track to achieve the objectives in the approved timeframe?Uncertain

Is the project on track to achieve the objectives within the approved budget?Yes

Project Overall Health Comments
Yellow
o Schedule: The SI Vendor’s schedule was still a draft on October 31, unapproved 101 days after its due date. The draft holds Go Live on June 24, 2028, by shortening the phases after a December Gap Analysis start. o Deliverables: Four of the SI Vendor’s 15 project plans are approved; the plans Gap Analysis needs are being submitted first. o Cost: Spending is 13% of the one-time budget. The cost table has no planned-spending comparison yet. o IV&V: The IV&V procurement, run through CDT, is expected to complete in February 2027; Gap Analysis is scheduled to begin in the first week of December 2026.
Focus Area/Rating Comments
Governance

Green
o The Project is following its approved Project Charter and Governance Plan. o The two October scheduling decisions, the December start of Gap Analysis and the sequence of the remaining SI Vendor plans, are logged as decision logs #17 and #18.
Time Management

Yellow
o No approved project schedule was in place on October 31. The schedule deliverable is 108 days past its contract due date and is being worked through weekly with the SI Vendor. o The approved requirements window closed August 31, 2026, with no requirements work started. Gap Analysis is now deferred to December 2026. o The SI Vendor’s latest draft puts Go Live on June 29, 2029, 10 months after the approved completion date.
Cost & Contract Management

Yellow
o The Project follows its contract management process and o The Project follows its contract management process and reports costs monthly by FAW category, as its approved Cost Management Plan provides, but without the burndown the plan calls for. o The cost table reconciles to the FAW baseline. Reported spending is $4.3 million (13%) of the $33.6 million one-time budget.
Scope Management

Green
o The approved scope is unchanged and no change requests were raised. The SI Vendor’s Requirements Management Plan is approved and its Scope Management Plan is in EDD review. o The requirements repository and traceability tool named in EDD’s Requirements Management Plan is not in place; the SI Vendor’s tool (OPC) is the subject of Risk 12. o The remaining SI Vendor plans are sequenced so those needed for Gap Analysis come first (decision #18); the two lists are not yet in the tracker.
Resources

Green
o The Project Team reported no staffing problems; the FAW and the organization chart agree on State staffing, but whether the FAW’s 8.6 PY of new positions are filled is not in the October records. o The SI Vendor replaced its Senior Project Manager effective October 1, 2026, at EDD’s request. Key staff onboarding was reported complete on October 30; Risk 13 remained open in the register.
Quality

Yellow
o The Project’s quality process will be set by its Quality Assurance Plan, an SI Vendor deliverable submitted October 21, 2026, and in EDD review; no approved quality process was in place during the month. o Four of 15 plans are approved and 13 submitted. One acceptance document is not yet submitted. o Risk 11 records that deliverable quality has improved but not consistently. Some recent submissions are paused while expected content is discussed.
Risk And Issues

Yellow
o The Project is not holding the weekly risk management meeting its approved Risk and Issue Management Plan requires; the register is updated through the weekly status cycle. o Four risk entries and one High-priority issue are open. The late SI Vendor status reports and the IV&V timing are not in the register.
Transition Readiness

Green
o Transition readiness is not yet applicable beyond change-management planning. The SI Vendor’s Organizational Change Management Plan was approved October 23, 2026.
Conditions For Approval

Green
No Stage 4 approval conditions apply.
Corrective Action

Green
No formal corrective action plan is in place.
Project Approval Documents