Independent Project Oversight Report (IPOR) Rating

3970-021 CalRecycle Integrated Information System (CRIIS)

A single enterprise solution to consolidate and manage CalRecycle’s 31 recyclable material and waste management systems that is scalable for future materials and program growth.

Project Details

Agency / State Entity Environmental Protection / Resources Recycling and Recovery, Department of
Total Cost $95,484,280
Last Approved Start Date 06/28/2024
Last Approved Finish Date 09/08/2026
Criticality Rating High
IPOR Reporting Period Overall IPOR Rating
05/01/2026 - 05/31/2026
Red
Independent Project Oversight Dashboard

Key Questions

Is the project on track to satisfy the customer's business objectives?No

Is the project on track to achieve the objectives in the approved timeframe?No

Is the project on track to achieve the objectives within the approved budget?No

Project Overall Health Comments
Red
The CRIIS project remains Red (escalation) status as it is not currently meeting the Special Project Report (SPR) no.1 baseline. However, stabilization efforts continue that will support establishing a new baseline.
Focus Area/Rating Comments
Governance

green icon Green
Project governance remains satisfactory, with leadership maintaining engagement during the execution pause. No new Executive Steering Committee (ESC) decisions were required or made this month.
Time Management

red icon Red
The Time focus area remains in a Red (escalation) status, as the project continues in a temporary execution pause following the termination of the primary solution integrator contract. • CalRecycle onboarded a group of contractors to conduct an independent assessment that will inform the project’s future delivery approach and support development of a high‑level replanning timeline.
Cost & Contract Management

red icon Red
The Cost and Contract focus area has a Red (escalation) rating, as no revised cost baseline exists. • Updated cost estimates will be developed after completing the independent assessment. Scope of work appears to be aligned with Lessons Learned, addressing gaps in architectural direction, customization control, and early risk identification to support a stable path forward before project restart.
Scope Management

red icon Red
Scope remains in Red (escalation) status as the project execution remains paused, and scope decisions are pending completion of the independent assessment.
Resources

red icon Red
Resources remain in Red (escalation) status as the project execution has paused and no delivery activities are authorized. • The IPO Manager will review the restart Staffing Plan when it becomes available to validate that resource availability aligns with the proposed re‑planning timeline.
Quality

red icon Red
Quality remains in Red (escalation) status as project quality activities remain paused. The IPO Manager will review the completed assessment when available to determine whether they provide the foundational clarity needed to re‑establish quality standards.
Risk And Issues

green icon Green
The Risk and Issue Management focus area continues to hold a Satisfactory rating, as Risk activity remains minimal during the project pause. No new risks were logged during this reporting period.
Transition Readiness

yellow icon Yellow
This focus area has a cautionary rating, as the transition planning remains on hold. The IPO Manager recommends identifying transition‑related dependencies that will need to be updated and incorporated into the future replanning timeline.
Conditions For Approval

yellow icon Yellow
The project must submit a Maintenance and Operations plan for CDT’s approval no later than six months before implementation. With the solution vendor contract now concluded and future milestones to be defined through SPR no. 2, this requirement will be reassessed once a new solution approach and updated schedule are established.
Corrective Action

green icon Green
None.