Independent Project Oversight Report (IPOR) Rating

Back to Listing

4265-076 Future Disease Surveillance System Project (FDSS)

The CDPH proposes to procure a disease surveillance system to address operational inefficiencies associated with manual processes and lack of access to timely and complete data to perform local and statewide disease surveillance.

Project Details

Agency / State Entity Health and Human Services / Public Health, Department of
Total Cost $45,848,096
Last Approved Start Date 04/01/2026
Last Approved Finish Date 09/30/2027
Criticality Rating Medium
IPOR Reporting Period Overall IPOR Rating
10/01/2026 - 10/31/2026
Green
Independent Project Oversight Dashboard

Key Questions

Is the project on track to satisfy the customer's business objectives?No

Is the project on track to achieve the objectives in the approved timeframe?No

Is the project on track to achieve the objectives within the approved budget?No

Project Overall Health Comments
Green
• The project’s overall health is Green but under watch due to the 3‑month schedule delay resulting from unplanned infrastructure and environment availability challenges. • The project is updating and re-baselining the schedule to reflect revised Go-Live and project completion dates. • The project is preparing supporting schedule-change documentation, including the impact analysis, revised project schedule, updated product roadmap, cost analysis for the SPR. • Training, Development, System Test, and Data Conversion environments are now available, enabling Sprint 4 development, testing, and data migration activities.
Focus Area/Rating Comments
Governance

Green
• This focus area is Green as the project is continuing to work through formalizing ESC‑approved schedule changes, including preparing the impact analysis, revised schedule, updated roadmap, and SPR. • The Executive Steering Committee meeting was held on October 29, 2026 and proposed go-live date were presented. • Project execution continued during Sprint 4, including functional testing, OCM planning, initiation of development and data migration activities, and commencement of CDPH program validation. • Observations and recommendations related to Agile practices were discussed with project leadership, and mitigation planning is underway. Progress will continue to be monitored through upcoming sprint activities and governance forums.
Time Management

Red
• The focus area is Red as there is 3 months environment setup delay to the project schedule and Go-Live. • Project is decided to extend the timeline by 3 months to deliver the planned scope. • Due to the implementation delay Program to plan for a one-time extension for the legacy system support. • Due to ongoing environment setup issues some of the Sprint 4 user stories were carryover to future sprints.
Cost & Contract Management

Green
Overall focus area is Green. Cost: Cost is trending towards Yellow due to the current FY funding impact of increase in cost associated with new licensing, and any additional cost impacts resulting from the schedule extension. • The project submitted a Fall BCP request for the shortfall funding FY 2028-2029. • The team identified an additional software license cost; however, the project can absorb the expense through a planned reallocation of existing line item within the SI contract. • The project is working on a three‑month extension, and the team is reviewing how this will change the overall costs. • Project expenditure for August 2026, based on actual reported to date, are at 8% of the total approved project cost. Contract: For this period there are no concerns. • Because of the three month extension, the project is reviewing amendment changes for all the contracts.
Scope Management

Green
• The focus area is Green as the planned deliverables remain within the approved scope, and delays were due to infrastructure availability rather than changes to scope. • Sprint 4 activities included progress on OCM planning and initiation of data migration and development efforts, while CDPH commenced program validation activities. • User stories not completed during Sprint 4 were deferred to future sprints and reprioritized through backlog refinement to maintain scope integrity. • The program validation stories and tasks have been added to the backlog and are being tracked separately, with validation and testing activities in progress.
Resources

Yellow
• The focus area under watch as it is trending Yellow, due to observed gaps in Agile process execution and Scrum practices. • Improvement opportunities were identified in sprint ceremonies, backlog management, and Agile reporting. Recommended actions include Agile training, Agile coaching support, and strengthened Scrum Master facilitation and increased Product Owner engagement to reinforce Agile practices and delivery transparency. • Project leadership has been engaged on the observations and recommendations, and planned mitigation actions will continue to be monitored through upcoming sprints. • Project Director availability remains under observation due to ongoing involvement in multiple CDPH strategic initiatives, which may impact oversight and decision turnaround.
Quality

Blue
• This focus area is Blue as the testing metrics evaluations by the project has not started, hence there is not enough data available to assess quality health.
Risk And Issues

Yellow
• The focus area is Yellow based on the current period environment and VDI concerns raised by the SI. • Sprint 4 scrum and retrospective highlighted training and facilitation gaps. • Funding constraints may create future risks depending on SPR outcomes. • The ongoing unplanned environment setup activities mitigation and action items continue. The impact analysis is in progress.
Transition Readiness

Green
• The focus area is Green as OCM work continues as per plan with no delays affecting stakeholder readiness, communications, or training preparation. • SI continued development in collab with CDPH readiness surveys, and training need assessment. • LHJ Change Champions and weekly OCM meetings ongoing. • Readiness Survey and Training Needs Assessment submitted and updated based on CDPH feedback. Both surveys are targeted to be sent on November 02, 2026.
Conditions For Approval

Green
• There were no conditions for S4 approval.
Corrective Action

Yellow
• This area is Yellow as there are corrective actions identified for this reporting period due to the 17+% variance and 3-month schedule extension.
Project Approval Documents