Independent Project Oversight Report (IPOR) Rating

Back to Listing

3900-074 Clean Truck Check- Vehicle Inspection System (CTC-VIS)

The California Air Resources Board proposes to create a compliance database for the upcoming Heavy-Duty Inspection and Maintenance program to house and store vehicle inspection data and determine compliance with the program.

Project Details

Agency / State Entity Environmental Protection / Air Resources Board, State
Total Cost $48,153,952
Last Approved Start Date 06/01/2023
Last Approved Finish Date 12/31/2026
Criticality Rating High
IPOR Reporting Period Overall IPOR Rating
07/01/2026 - 07/31/2026
Green
Independent Project Oversight Dashboard

Key Questions

Is the project on track to satisfy the customer's business objectives?Yes

Is the project on track to achieve the objectives in the approved timeframe?Yes

Is the project on track to achieve the objectives within the approved budget?Yes

Project Overall Health Comments
Green
The overall health of the project continued to be Green (satisfactory) based on observations in all focus areas. • The project remained on schedule and was within the approved scope and cost in the July 2026 reporting period. • During this reporting period, the project continued work on Sprints 1 and 2 for Phase 2 Release 4. • Overall, the project progress has maintained sustained delivery momentum with effective coordination across teams.
Focus Area/Rating Comments
Governance

Green
This focus area remained Green (satisfactory) during this reporting period. • The Executive Steering Committee (ESC) meeting held on July 8, 2026, confirmed that the project is on track to achieve its objectives within the baselined scope, schedule, and budget. • The project’s governance structure continues to operate effectively, enabling consistent project delivery and maintaining confidence in the strength of management controls. • The Independent Project Oversight (IPO) Manager continued to emphasize the importance of continuing timely communication and sustaining stakeholder awareness of key project decisions. Consistent with oversight best practices, the ongoing participation by program, business, technical, and control agency stakeholders is supporting informed decision‑making and the successful delivery of development efforts.
Time Management

Green
This focus area remained Green (satisfactory) during this reporting period. • The project remains on schedule as planned, supported by disciplined execution across teams. • The IPO Manager recommends that continued project progress and adherence to near-term sprint commitments be complemented by enhanced identification and management of schedule risks related to competing priorities, to ensure sustained delivery performance and the successful achievement of long-term project outcomes. • The IPO Manager recommended continuing the practice of updating the project schedule to include the names of individuals for each activity to ensure accountability and keep the master schedule document updated as needed.
Cost & Contract Management

Green
This focus area remained Green (satisfactory) during this reporting period. • The Contract Amendment 3 was completed on June 04, 2026. • The project continued to analyze the root cause of the AWS cost increases. The IPO manager continues to recommend that the project assess, monitor, and report any potential cost-related risks or issues associated with the actual expenditure, relative to approved budgets and forecasts, to support informed financial management and any required corrective action. • The IPO Manager has raised concern that the CARB Information Technology Procurement, Contract, and Reporting (ITPCR) section staffing issues could impact contract management-related activities.
Scope Management

Green
This focus area remained Green (satisfactory) in this reporting period. • During this reporting period, the overall Phase 2 14-month extended DDI Scope is at 33% completion. • The project is currently working on the tasks associated with Phase 2 Release 4 Sprints 1 and 2. • Program and business representatives are actively reviewing and validating proposed system functions and features to confirm that solution requirements accurately reflect business needs and strategic objectives. • The project is aligned with Agile governance, and requirements management best practices, by fostering stakeholder engagement, maintaining requirements traceability, and supporting the incremental delivery of prioritized capabilities. • The IPO manager recommends that project teams continuously validate the business value of upcoming requirements, by clearly distinguishing between system functions and features that are critical versus those that are discretionary.
Resources

Green
This focus area remained Green (satisfactory) during this reporting period. • The project continued to successfully complete scheduled tasks with no concerns about resource availability in any of the project-specific areas. • The CARB Information Technology Procurement, Contract, and Reporting (ITPCR) section is again experiencing staffing-related issues. At this time, the anticipated impact to the project remains low. • The IPO Manager recommends that the project continue to evaluate actual resource capacity versus planned allocation, consistent with Project Resource Management best practices. Without regular validation, there is a risk that resource assumptions may become outdated, leading to misalignment between available skillsets and evolving project demands.
Quality

Green
This focus area remained in Green (satisfactory) during this reporting period. • The project has continued to follow robust test and defect management practices throughout all sprints, and has maintained the trend of high-test pass rates and minimal defects. • The IPO manager recommends that the project apply a disciplined cost‑benefit evaluation to support informed decision‑making, to help prevent low‑value or discretionary changes from diverting focus from critical priorities, and to reduce the risk of scope creep, resource strain, and diminished return on investment.
Risk And Issues

Green
This focus area remained in Green (satisfactory)during this reporting period. • The risks and issues are actively monitored, managed, and tracked. • No new issues were logged during the July reporting period. • Two new risks were opened related to AWS cloud costs and intermittent production degradation issues. The increased AWS costs are not anticipated to trigger a Special Project Report. • The IPO manager recommends that the project conduct regular retrospective sessions and ensure that identified improvement actions are documented, prioritized, and incorporated during project execution. This practice supports continuous improvement, strengthens management controls, and aligns with oversight best practices for effective project delivery.
Transition Readiness

Green
This focus area remained in Green (satisfactory) during this reporting period, as the program outreach and support activities continued to be effective in raising awareness of the SB210 regulation to bring fleets into the reporting system. • Over 794,000 vehicles are registered in the CTC-VIS database and have generated revenue of over $77 million from fee collection. • The IPO Manager reiterated the recommendation that the Program team formally document the outreach team’s best practices, performance metrics, and lessons learned, capturing both achievements and areas requiring improvement. This documentation will provide valuable input for updating the Post‑Implementation Evaluation Report (PIER) upon project completion.
Conditions For Approval

Green
None
Corrective Action

Green
None.