Independent Project Oversight Report (IPOR) Rating

7350-095 Labor Enforcement Task Force Project (LETF Project)

Pursuant to Assembly Bill 175 (Chapter 255, 2021), the sum of $30,000,000 was appropriated from the Labor and Workforce Development Fund for support of The Department of Industrial Relations (DIR) for strategic enforcement focused on construction, alteration, and repair projects, subject to the provisions of Section 1785 of the Labor Code. $10,000,000would be allocated to DIR OIS in an effort to upgrade the current Public Works data systems and create a technical capability for analytics using this data.

Project Details

Agency / State Entity Labor and Workforce Development / Industrial Relations, Department of
Total Cost $40,292,475
Last Approved Start Date 06/22/2023
Last Approved Finish Date 06/30/2025
Criticality Rating Medium
IPOR Reporting Period Overall IPOR Rating
12/01/2024 - 12/31/2024
Red

Key Questions

Is the project on track to satisfy the customer's business objectives?Uncertain

Is the project on track to achieve the objectives in the approved timeframe?No

Is the project on track to achieve the objectives within the approved budget?Uncertain

Project Overall Health Comments
Red
Project Overall Health remained in Red (critical) status: • Pending the SPR submittal in January 2025. • The contract manager resource constraint remains. >IPO Manager recommended the use of a vacant IT position to hire a contract manager critical need within OIS. • The schedule has slipped 12+ months and cannot meet the approved schedule. • The cost changes cannot be determined until the SPR is reviewed and approved with the CDT.
Focus Area/Rating Comments
Governance

green icon Green
Governance remained in Green (satisfactory) status: • The contract manager resource constraint continued. • Reminder that the PSRs need to be submitted no later than the 5th business day of the following month. - i.e., the December PSR was due January 8, 2025.
Time Management

red icon Red
Time Management remained in Red (critical) status: • Pending the SPR. • The IPO Manager observed that there is no schedule available for the Release 2 development work. > The Master Project Schedule Plan needs to be updated for Phase/Release 2 to reflect a solid draft schedule in advance of re-releasing the RFP/SOW for the SI. • The Special Project Report (SPR) (draft) to re-baseline the schedule, as well as scope and cost, has been reviewed with the IPO Manager. It is very slim on Schedule content for Release 2. >The IPO Manager recommends that the PM update the Release 2 Schedule to be realistic. • The schedule delay has been estimated to take 12+ months. This is dependent on the procurement which is dependent on the RFP/SOW updates by the DIR contract manager.
Cost & Contract Management

red icon Red
Cost & Contract Management remained in Red (critical) status: • Pending the SPR. • The IPO Manager observed that costs need to be re-baselined due to the schedule delay for Release 2. This change required an SPR. >The SPR will re-set the cost roadmap baseline going forward. • The SPR cost update will be based on an estimated schedule and related expenditures through FY2025/26. Costs impacted include increased SI and other ancillary contract costs, oversight costs, etc., and reappropriation of FY2024/2025 Project funds. • The procurement for the Release 2 SI was pending DIR resource to complete the necessary artifacts prior to solicitation release.
Scope Management

red icon Red
Scope Management remained in Red (critical) status: • This focus area was not addressed this period. • Pending the SPR.
Resources

green icon Green
Resources remained in Green (satisfactory) status: • The Project continued to recruit for 2.0 approved vacant IT positions, for 18 months. IT positions approved at 10.0. >No update on Project program staffing on-boarded (32.0 positions approved) nor any recruitment issues. • The sole contract manager is an ongoing resource constraint. >The IPO Manager recommended that the DIR fill a vacant IT position for the role of full-time contract manager to manage all IT project contracts. • The SI for Release 2 is pending DIR solicitation inputs. • The IV&V consultants were on-boarded following contract award on December 10, 2024.
Quality

green icon Green
Quality remained in Green (satisfactory) status: • The requirement for IV&V consulting services remains outstanding. > The IPO Manager observed that the contract for IV&V services was awarded on 12/10/2024, and the on-boarding process was begun.
Risk And Issues

green icon Green
Risks and Issues remained in Green (satisfactory) status: • This focus area was not addressed this period.
Transition Readiness

green icon Green
Transition Readiness remained in Green (satisfactory) status: • This focus area was not addressed this period.
Conditions For Approval

green icon Green
Conditions for Approval remained in Green (satisfactory) status. The PW/LETF Project has completed all conditions of approval. This item is considered COMPLETE. • 1. IV&V consulting service condition status: The contract was awarded and the consultants began the on-boarding process.
Corrective Action

green icon Green
None.
; Website Accessibility Certification

2025-02-07 - Release-11