Independent Project Oversight Report (IPOR) Rating

1115-004 Cannabis Data Warehouse and Business Intelligence Reporting Tool (BI Tool)

The Department of Cannabis Control (Department) seeks to improve business and technical internal users’ access to data from our licensing, enforcement, compliance, and track and trace system. The Department wants to empower these users’ abilities to build their own reports without the need to understand SQL or other coding languages. Additionally, the Department wants the capability to build external facing dashboards to allow external users that ability to interact with data in charts and graphs to understand trends in the cannabis industry.

Project Details

Agency / State Entity Business, Consumer Services, and Housing / Department of Cannabis Control
Total Cost $3,041,932
Last Approved Start Date 05/06/2024
Last Approved Finish Date 05/05/2025
Criticality Rating Low
IPOR Reporting Period Overall IPOR Rating
10/01/2024 - 10/31/2024
Green

Key Questions

Is the project on track to satisfy the customer's business objectives?Yes

Is the project on track to achieve the objectives in the approved timeframe?Yes

Is the project on track to achieve the objectives within the approved budget?Yes

Project Overall Health Comments
Green
• The project team is effectively managing all focus areas and aligns with baseline project management plans. The Solution Partners (SP) and DCC teams are collaborating in support of the project. • This report covers October 1- October 30, 2024
Focus Area/Rating Comments
Governance

green icon Green
• The project roles and responsibilities are established and documented. • The team maintains all recurring meetings in support of the project and follows governance practices. • The project’s governance practices align with the current approved Governance plan.
Time Management

green icon Green
• Schedule re-baseline in review based on schedule delay. • The IPO will continue to monitor project schedule.
Cost & Contract Management

green icon Green
• The project is tracking monthly costs, and current expenses are within the planned budget amount.
Scope Management

green icon Green
•The project is aligned with approved project scope. •Scope and Requirement management plans are in place and being followed.
Resources

green icon Green
• All vendor staff have been onboarded. • The project is actively managing its resources. • Appropriate resource management and contract management practices are being followed in accordance with the Resource Management section in master Project Management Plan.
Quality

green icon Green
• Quality control expectations and best practices are described in the Quality Management section of the Project Management Plan.
Risk And Issues

green icon Green
•Risks are being actively monitored, managed and tracked. •The project team is adhering to risk monitoring practices as identified in the Risk Management Plan.
Transition Readiness

blue icon Blue
• Not enough information to make an assessment.
Conditions For Approval

green icon Green
• No conditions for approval.
Corrective Action

green icon Green
• No corrective action plans in place.