Independent Project Oversight Report (IPOR) Rating

1115-004 Cannabis Data Warehouse and Business Intelligence Reporting Tool (BI Tool)

The Department of Cannabis Control (Department) seeks to improve business and technical internal users’ access to data from our licensing, enforcement, compliance, and track and trace system. The Department wants to empower these users’ abilities to build their own reports without the need to understand SQL or other coding languages. Additionally, the Department wants the capability to build external facing dashboards to allow external users that ability to interact with data in charts and graphs to understand trends in the cannabis industry.

Project Details

Agency / State Entity Business, Consumer Services, and Housing / Department of Cannabis Control
Total Cost $3,041,932
Last Approved Start Date 05/06/2024
Last Approved Finish Date 05/05/2025
Criticality Rating Low
IPOR Reporting Period Overall IPOR Rating
01/01/2025 - 01/31/2025
Green

Key Questions

Is the project on track to satisfy the customer's business objectives?Yes

Is the project on track to achieve the objectives in the approved timeframe?Yes

Is the project on track to achieve the objectives within the approved budget?Yes

Project Overall Health Comments
Green
• The project team is effectively managing all focus areas and aligns with baseline project management plans. The Solution Partners (SP) and DCC teams collaborated to a successful implementation of the project. • This report covers January 1, 2025-January 31, 2025
Focus Area/Rating Comments
Governance

green icon Green
• The project roles and responsibilities are established and documented. • The team maintains all recurring meetings in support of the project and follows governance practices. • The project’s governance practices align with the current approved Governance plan.
Time Management

green icon Green
• Project implementation was successful and completed before original proposed end date of May 5, 2025.
Cost & Contract Management

green icon Green
• The project was completed under original cost projections. The project did not need to utilize additional optional implementation costs.
Scope Management

green icon Green
• The project is aligned with approved project scope. • Scope and Requirement management plans are in place and are being followed. • Scope of the project was implemented.
Resources

green icon Green
• The project is actively managing its resources. • Appropriate resource management and contract management practices are being followed in accordance with the Resource Management section in the master Project Management Plan.
Quality

green icon Green
• Quality control expectations and best practices are described in the Quality Management section of the Project Management Plan.
Risk And Issues

green icon Green
• Risks are being actively monitored, managed and tracked. • No current Risks or Issues were reported during this reporting period.
Transition Readiness

green icon Green
• All transition activities were completed this reporting period.
Conditions For Approval

green icon Green
• No conditions for approval.
Corrective Action

green icon Green
• No corrective action plans in place.