Independent Project Oversight Report (IPOR) Rating

2740-218 Legacy System Stabilization (LSS)

The Department of Motor Vehicles (DMV) proposes to restructure the Front End Applications Sustainability effort from migrating only the Vehicle Registration, Occupational Licensing and Cashiering front-end application to a more sustainable technology platform; to now the Legacy System Stabilization effort that will stabilize all the Department’s legacy applications, systems, and hardware to reduce the risk of catastrophic failures. This will enable the Department to address external mandates and maintain DMV service delivery to Californians, while preparing for the DMV Modernization effort.

Project Details

Agency / State Entity Transportation / Motor Vehicles, Department of
Total Cost $73,718,640
Last Approved Start Date 01/03/2019
Last Approved Finish Date 06/30/2025
Criticality Rating Low
IPOR Reporting Period Overall IPOR Rating
06/01/2023 - 06/30/2023
Green

Key Questions

Is the project on track to satisfy the customer's business objectives?Yes

Is the project on track to achieve the objectives in the approved timeframe?Yes

Is the project on track to achieve the objectives within the approved budget?Yes

Project Overall Health Comments
Green
The LSS Project oversees the DMV’s legacy systems’ maintenance, operations, and stabilization while the DMV migrates its business functions and data to the new Digital Experience Platform (DXP). A governance process is in place, and weekly sponsor and steering committee meetings include schedule, cost, and escalation items. After carefully considering and reviewing the LSS Project’s scope, historical progress, and the SPR submitted in June 2023, the CDT IPO has downgraded this project’s complexity to ”Low.” As such, CDT IPO’s active oversight of the LSS Project is no longer required, and the June 2023 IPOR will be the final IPOR released.
Focus Area/Rating Comments
Governance

green icon Green
Approved governance and organizational change management (OCM) processes are in place.
Time Management

green icon Green
The Project developed a Master Integrated Project Schedule that meets the CDT Independent Project Oversight (IPO) recommendations and tracks the progress of the sub-projects via sub-project key milestones.
Cost & Contract Management

green icon Green
The Project indicated that the costs were coming in under budget. The LSS Project submitted an SPR in June 2023 to appropriately extend the project and rebaseline costs.
Scope Management

green icon Green
The Project indicated that there are no changes to the approved scope.
Resources

green icon Green
The Project has not identified any resource issues.
Quality

green icon Green
The Project has submitted the Quality Assurance Plan.
Risk And Issues

green icon Green
The Project has scheduled project risks and issues management meetings. No new risks or issues were identified in this reporting period.
Transition Readiness

green icon Green
A Transition Readiness Plan is in place, which identifies the Project’s planned transition coincides with the implementation and retirement of each business function as the DXP Project evolves. The transition will commence via the planned OCM activities.
Conditions For Approval

green icon Green
N/A
Corrective Action

green icon Green
N/A