Independent Project Oversight Report (IPOR) Rating

7730-209 Enterprise Data to Revenue 2 (EDR2)

The Franchise Tax Board proposes to implement Phase 2 of their Tax Systems Modernization Plan. Phase 2 transitions Audit, Filing Enforcement, and Underpayment to the Enterprise Data, Case Management and Modeling platform.

Project Details

Agency / State Entity Government Operations / Franchise Tax Board
Total Cost $766,091,572
Last Approved Start Date 07/01/2021
Last Approved Finish Date 01/02/2026
Criticality Rating Medium
IPOR Reporting Period Overall IPOR Rating
10/01/2024 - 10/31/2024
Green

Key Questions

Is the project on track to satisfy the customer's business objectives?Yes

Is the project on track to achieve the objectives in the approved timeframe?Yes

Is the project on track to achieve the objectives within the approved budget?Yes

Project Overall Health Comments
Green
The overall Health of the project is Green. The project is effectively managing all focus areas and aligns with the baseline project management plans. The Solution Partners (SP) and FTB teams fully collaborate and support the project.
Focus Area/Rating Comments
Governance

green icon Green
The Governance teams maintain all recurrent meetings in support of the project and follow the governance best practices.
Time Management

green icon Green
The project schedule is on track and the schedule performance index (SPI) shows no variance. As of October, the overall project completion percentage is 80%.
Cost & Contract Management

green icon Green
Per the October 2024 Project Status Report, the project expenses are within the planned budget and 54.9% of the total project cost has been expended. The Cost Performance Index (CPI) shows no variance.
Scope Management

green icon Green
Milestone completion is on-track. Change Requests (CRs) are effectively managed.
Resources

green icon Green
Roles and Responsibilities are clearly defined, and the number of SP resources continues to be adequate and maintained at full capacity. Project resources demonstrate high level professionalism and appropriate knowledge. Project reporting is adequate and effective.
Quality

green icon Green
The project continues to diligently monitor quality assurance and quality control and to apply best practices to ensure expectations are being met.
Risk And Issues

green icon Green
The Project Management Oversight (PMO) team effectively manages, tracks, and maintains a risk/issue log in Team Foundation Server (TFS). The FTB project team collaborates with the CDT IPO team and meets weekly to discuss the project progress and risks/issues.
Transition Readiness

green icon Green
The transition readiness aligns with the transition plan. Each role identified in the transition plan follows a 9-month progressive knowledge development model: Pre-Crawl, Crawl, Walk, Run, and Transition.
Conditions For Approval

green icon Green
N/A
Corrective Action

green icon Green
No corrective action plans are required at this time.
; Website Accessibility Certification

20240624.1 - Release-59